A sector’s or portfolio’s projects with their weights, progress, milestones, risks and approvals.
All sectors
Σ (weight × actual progress)
The next 60 days, and those past due
of 45 open risks
2 of them late
Shown by your permissionsProject Management Office: 36 projects — everything in your scope
The big figure is the weight-based progress; pick a unit to see its projects alone, pick it again to go back.
Each project’s relative weight in its portfolio, progress against plan, risks and approvals.
Weight-based progress: 52%
| Project | Portfolio | Weight | Earned / planned | Approved budget | Risks | Pending approvals |
|---|---|---|---|---|---|---|
| Hama National Hospital Upgrade & Extension | Health, Education & Industrial Recovery Portfolio | 27.3% | 57% | SYP 16B | 3 | 3 |
| Sheikh Najjar Industrial City Rehabilitation | Health, Education & Industrial Recovery Portfolio | 25.2% | 39% | SYP 7.2B | 2 | — |
| Latakia University Technical Engineering Faculty Extension | Health, Education & Industrial Recovery Portfolio | 24.5% | 52% | SYP 4B | 1 | — |
| Aleppo 230 kV Substations Rehabilitation | Energy & Water Portfolio | 24.4% | 68% | SYP 10.3B | 3 | 1 |
| Preparing the 2026–2028 Medium-Term Plan & Governorate Plans | Planning, Statistics & Capability Portfolio | 23.8% | 70% | SYP 80M | 0 | — |
| Al-Mayadin General Hospital | Health, Education & Industrial Recovery Portfolio | 23.0% | 2% | SYP 5.3B | 1 | — |
| Unified Government e-Services Platform | Digital Government Services & Data Portfolio | 21.8% | 58% | SYP 2.2B | 10 | 7 |
| 20 MW Qalamoun Solar Field | Energy & Water Portfolio | 20.9% | 58% | SYP 2.4B | 0 | — |
| Hasakah Wheat Digital Crop Survey | Planning, Statistics & Capability Portfolio | 20.5% | 63% | SYP 160M | 1 | — |
| e-Learning Platform & Computer Labs for Raqqa Schools | Planning, Statistics & Capability Portfolio | 19.8% | 4% | SYP 187.5M | 0 | — |
| Madinat al-Salam Drinking-Water Network (Quneitra) | Energy & Water Portfolio | 19.1% | 97% | SYP 1.7B | 1 | 1 |
| Darayya Replacement Housing | Reconstruction & Infrastructure Portfolio | 18.3% | 42% | SYP 29.5B | 4 | 1 |
| Ministries Performance Follow-up & National Dashboards | Planning, Statistics & Capability Portfolio | 18.3% | 76% | SYP 245M | 0 | — |
| Suwayda Drinking-Water Network from Al-Ain Dam | Energy & Water Portfolio | 18.2% | 36% | SYP 1.1B | 0 | — |
| National Project Risk & Continuity Framework | Planning, Statistics & Capability Portfolio | 17.6% | 100% | SYP 90M | 0 | — |
| Baniyas Pilot Seawater Desalination Plant | Energy & Water Portfolio | 17.4% | 8% | SYP 825M | 1 | — |
| National Statistical Indicators & Open Data Portal | Digital Government Services & Data Portfolio | 17.3% | 62% | SYP 537.5M | 1 | — |
| Integrated Public Financial Management System — Phase 1 | Government Digital Infrastructure & Systems Portfolio | 16.4% | 61% | SYP 1.6B | 3 | 2 |
| Government Backup Data Centre, Homs — Phase 2 | Government Digital Infrastructure & Systems Portfolio | 16.4% | 72% | SYP 3.7B | 2 | 1 |
| Deir ez-Zor Suspension Bridge Reconstruction | Reconstruction & Infrastructure Portfolio | 16.3% | 2% | SYP 13B | 1 | — |
| Medium-Term Plan Implementation Tracker (ministries & governorates) | Digital Government Services & Data Portfolio | 16.3% | 1% | SYP 700M | 0 | 2 |
| Douma Wastewater Treatment Plant | Reconstruction & Infrastructure Portfolio | 16.1% | 44% | SYP 8.6B | 2 | — |
| Government Cloud & Ministry Systems Migration | Government Digital Infrastructure & Systems Portfolio | 15.9% | 47% | SYP 1.3B | 1 | — |
| e-Litigation & Judicial Notification Platform — Release 2 | Digital Government Services & Data Portfolio | 15.6% | 91% | SYP 460M | 0 | — |
| Government Services Mobile App — New Release | Digital Government Services & Data Portfolio | 15.6% | 64% | SYP 315M | 0 | — |
| Government Network Cybersecurity Programme | Government Digital Infrastructure & Systems Portfolio | 15.2% | 88% | SYP 965M | 1 | — |
| Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate | Reconstruction & Infrastructure Portfolio | 14.6% | 33% | SYP 6B | 1 | — |
| Civil Registry Automation & Governorate Link-up | Government Digital Infrastructure & Systems Portfolio | 13.6% | 6% | SYP 600M | 0 | — |
| Digital Signature & e-Verification of Government Documents — Phase 1 | Digital Government Services & Data Portfolio | 13.4% | 100% | SYP 205M | 0 | — |
| Population & Housing Census Preparation — Phase 1 | Reconstruction & Infrastructure Portfolio | 12.1% | 2% | SYP 1.2B | 1 | — |
| Ministry of Finance e-Archiving | Government Digital Infrastructure & Systems Portfolio | 11.5% | 95% | SYP 355M | 1 | — |
| Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals | Reconstruction & Infrastructure Portfolio | 11.3% | 79% | SYP 1.9B | 2 | — |
| Government Fibre Backbone — Damascus–Homs Segment | Reconstruction & Infrastructure Portfolio | 11.3% | 55% | SYP 3.3B | 2 | — |
| Government HR System — Employee Self-Service | Government Digital Infrastructure & Systems Portfolio | 11.1% | 100% | SYP 285M | 0 | — |
| Unified Government Contact Centre & AI Assistant | Reconstruction & Infrastructure Portfolio | — | 0% | SYP 2.8B | 0 | — |
| National Development & Reconstruction Forum 2027 | Digital Government Services & Data Portfolio | — | 0% | SYP 600M | 0 | — |
Relative weight in the portfolio: the project’s share of its portfolio’s budget, adjusted by its priority score; each portfolio’s weights add to 100%; proposed and cancelled projects carry none.
What falls due soon and what is late, the open risk map, and what waits for a decision.
The next 60 days, and those past due
of 45 open risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 3 · Critical | 1 · Critical |
| 4 | 0 · Low | 0 · Medium | 4 · Medium | 9 · High | 2 · Critical |
| 3 | 0 · Low | 0 · Low | 12 · Medium | 5 · Medium | 3 · High |
| 2 | 0 · Low | 0 · Low | 3 · Low | 1 · Medium | 2 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
What waits for a decision on these projects