PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+5

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦58% done against 57% planned⁩.

⁦SPI 1⁩.⁦02⁩, ⁦CPI 1⁩.⁦01⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.1Rehabilitate core energy, water and transport infrastructure

Main initiative

SI-2.1.3Renewable energy & non-conventional water

Contribution to the initiative⁦74%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

Annual work-plan line
WP-2025-010
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦58%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦32%⁩

7 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Detailed design⁦7%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Supply⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦90%⁩ of budget

SYP1.4B/ SYP2.4BSYP23.8Mprojected saving(⁦1.0%⁩)
Actual spend
SYP1.4B
Committed
SYP2.2B
Approved budget
SYP2.4B
Estimate at completion
SYP2.4B

Next milestones

  • Provisional acceptance⁦2027-02-20⁩was ⁦2027-02-26⁩On track
  • Closure⁦2027-04-22⁩was ⁦2027-04-30⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SYP 130M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦7⁩ of ⁦12⁩ approved

  • Project plan & baseline010-D1 · V1 · CRT-010-01⁦3%⁩Eng. Rami Youssef2025-06-102025-06-10Approved
  • Monitoring & reporting010-D2 · V1 · CRT-010-02⁦3%⁩Eng. Wassim Al-Azm2025-08-122025-08-12Approved
  • Detailed design010-D3 · V1 · CRT-010-03⁦7%⁩Eng. Wassim Al-Azm2025-10-132025-10-13Approved
  • Permits & approvals010-D4 · V1 · CRT-010-04⁦6%⁩Salma Al-Zaim2025-12-152025-12-15Approved
  • Site works & excavation010-D5 · V1 · CRT-010-05⁦13%⁩Salma Al-Zaim2026-02-162026-02-16Approved
  • Structure010-D6 · V1 · CRT-010-06⁦13%⁩Eng. Rami Youssef2026-04-192026-04-19Approved
  • Finishes010-D7 · V1 · CRT-010-07⁦13%⁩Eng. Wassim Al-Azm2026-06-212026-06-21Approved
  • Supply010-D8 · V1⁦10%⁩Eng. Rami Youssef66 days overdue2026-08-23Submitted
  • Installation010-D9 · V0⁦9%⁩Eng. Wassim Al-Azm4 days overdue2026-10-24Draft
  • Testing & commissioning010-D10 · V0⁦9%⁩Salma Al-ZaimIn 59 days2026-12-26Draft
  • Provisional acceptance010-D11 · V0⁦7%⁩Eng. Wassim Al-AzmIn 121 days2027-02-26Draft
  • Final acceptance010-D12 · V0⁦7%⁩Salma Al-ZaimIn 184 days2027-04-30Draft

Team, contracts & documents

Team

2 members

Eng. Rami Youssef · Director, Renewable Energy & Environment ProjectsEng. Wassim Al-Azm · Director General, Infrastructure & Reconstruction Projects
  • Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsProject managerP-028rami.youssef@psa.gov.sy⁦45%⁩
  • Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsProject ownerP-013wassim.alazm@psa.gov.sy⁦15%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close