PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy
20 MW Qalamoun Solar Field
Add to watchlistA 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.
Project managerEng. Rami YoussefProject sponsorSalma Al-ZaimProgrammeEnergy & Water Systems Rehabilitation Programme
Budget (BAC)
SYP 2.4B
Actual cost
SYP 1.4B
57% of budget
Progress
58%Awaiting acceptance 10%
Estimate at completion
SYP 2.4B
SPI · CPI
1.02Schedule performance index · 1.021.01Cost performance index · 1.01
Forecast finish
2027-04-22
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started