20 MW Qalamoun Solar Field
Add to watchlistA 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure26 February 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-08-12 | 2025-09-25 | +44 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-15 | 2026-03-03 | +78 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-06-21 | 2026-10-26 | +127 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-12-26 | 2027-03-05 | +69 days | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-04-30 | 2027-04-30 | On time | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
58%Awaiting acceptance
10%Not handed in
32%Deliverable flow
Display options
| Project plan & baseline010-D1 | 3% | CRT-010-01 | Approved | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Eng. Wassim Al-Azm | 2025-06-10 | V1 | 3 of 3 |
| Monitoring & reporting010-D2 | 3% | CRT-010-02 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2025-08-12 | V1 | 3 of 3 |
| Detailed design010-D3 | 7% | CRT-010-03 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2025-10-13 | V1 | 3 of 3 |
| Permits & approvals010-D4 | 6% | CRT-010-04 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2025-12-15 | V1 | 3 of 3 |
| Site works & excavation010-D5 | 13% | CRT-010-05 | Approved | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2026-02-16 | V1 | 3 of 3 |
| Structure010-D6 | 13% | CRT-010-06 | Approved | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Eng. Wassim Al-Azm | 2026-04-19 | V1 | 3 of 3 |
| Finishes010-D7 | 13% | CRT-010-07 | Approved | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-06-21 | V1 | 3 of 3 |
| Supply010-D8 | 10% | — | Submitted | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy | Eng. Wassim Al-Azm | 2026-08-23 | V1 | 1 of 3 |
| Installation010-D9 | 9% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2026-10-24 | V0 | 0 of 3 |
| Testing & commissioning010-D10 | 9% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2026-12-26 | V0 | 0 of 3 |
| Provisional acceptance010-D11 | 7% | — | Draft | Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy | Eng. Wassim Al-Azm | 2027-02-26 | V0 | 0 of 3 |
| Final acceptance010-D12 | 7% | — | Draft | Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy | Eng. Wassim Al-Azm | 2027-04-30 | V0 | 0 of 3 |
| Total · 12 | 100% |