PRJ-2026-010On track4ExecutionConstructionIn progressDelivered by:Ministry of Energy

20 MW Qalamoun Solar Field

Add to watchlist

A 20 MW photovoltaic field near An-Nabk feeding the public grid, with a substation and a 66 kV connection line.

Budget (BAC)

SYP 2.4B

Actual cost

SYP 1.4B

⁦57%⁩ of budget

Progress

⁦58%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 2.4B

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure26 February 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate26 February 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-03-27⁩
ApprovedPRJ-2026-01020 MW Qalamoun Solar Field

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-010
Project
20 MW Qalamoun Solar Field
Portfolio
Energy & Water Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Rami Youssef

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-03-02⁩

Baseline finish

⁦2027-04-30⁩

Forecast finish

⁦2027-04-22⁩

SPI

1.02

MilestonePlannedForecastSlip
Project plan approved⁦2025-08-12⁩⁦2025-09-25⁩+44 days
Designs approved⁦2025-12-15⁩⁦2026-03-03⁩+78 days
Build complete⁦2026-06-21⁩⁦2026-10-26⁩+127 days
Testing & acceptance complete⁦2026-12-26⁩⁦2027-03-05⁩+69 days
Final handover⁦2027-04-30⁩⁦2027-04-30⁩0

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2025-06-10⁩Eng. Rami Youssef
Monitoring & reporting⁦3%⁩⁦2025-08-12⁩Eng. Wassim Al-Azm
Detailed design⁦7%⁩⁦2025-10-13⁩Eng. Wassim Al-Azm
Permits & approvals⁦6%⁩⁦2025-12-15⁩Salma Al-Zaim
Site works & excavation⁦13%⁩⁦2026-02-16⁩Salma Al-Zaim
Structure⁦13%⁩⁦2026-04-19⁩Eng. Rami Youssef
Finishes⁦13%⁩⁦2026-06-21⁩Eng. Wassim Al-Azm
Supply⁦10%⁩⁦2026-08-23⁩Eng. Rami Youssef
Installation⁦9%⁩⁦2026-10-24⁩Eng. Wassim Al-Azm
Testing & commissioning⁦9%⁩⁦2026-12-26⁩Salma Al-Zaim
Provisional acceptance⁦7%⁩⁦2027-02-26⁩Eng. Wassim Al-Azm
Final acceptance⁦7%⁩⁦2027-04-30⁩Salma Al-Zaim
Accepted with a certificate⁦58%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0041Lower world PV prices allow a larger field within the allocation12AcceptEng. Rami Youssef

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Rami Youssef
Project ownerDeliverable status and acceptance datesFortnightlyEng. Rami Youssef
PMOData and indicator updatesWeeklyEng. Rami Youssef
BeneficiariesWhat changes and whenAt each milestoneEng. Rami Youssef
Team memberRoleAllocation
Eng. Rami YoussefProject manager⁦45%⁩
Eng. Wassim Al-AzmProject owner⁦15%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Rami Youssef
Review cadenceAuto-filled
A flash test on a sample of each panel batch
Next reviewAuto-filled
⁦2026-11-09⁩
Quality criterionThresholdNowMet
Actual panel output≥ 97% of rated output94.8% in batch 6No
Performance ratio of live plants80% or more83%Yes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
Solar energy generated0 MWh / year31000 MWh / yearEng. Rami Youssef
Value of energy delivered to the public grid0 SYP million232.5 SYP millionHuda Al-Dandal

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Rami YoussefDirector, Renewable Energy & Environment ProjectsSubmitted—⁦2025-03-27⁩ 11:26
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2025-03-31⁩ 13:58
3Technical acceptance — project ownerTechnical acceptanceEng. Wassim Al-AzmProject ownerApproved—⁦2025-04-03⁩ 14:05
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2025-04-07⁩ 12:21
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2025-04-08⁩ 13:58
6Sponsor approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2025-04-13⁩ 11:26

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2025-03-31⁩

Technical acceptance — project owner

Eng. Wassim Al-Azm

Approved⁦2025-04-03⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2025-04-07⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2025-04-08⁩

Sponsor approval

Salma Al-Zaim

Approved⁦2025-04-13⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Rami Youssef on ⁦2025-03-27⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2025-03-31⁩ at ⁦13:58⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Eng. Wassim Al-Azm · Project owner

    Approved · ⁦2025-04-03⁩ at ⁦14:05⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-07⁩ at ⁦12:21⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-04-08⁩ at ⁦13:58⁩

  5. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2025-04-13⁩ at ⁦11:26⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-03-27⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Rami Youssef

  2. V1Returned for edit⁦2025-03-13⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Rami Youssef