RSK-004120 MW Qalamoun Solar Field
Lower world PV prices allow a larger field within the allocation
A risk's detail, response, contingency and residual risk.
Risk statement
From enabler to opportunity to benefit — with the actions that seize it and the fallback
Enabler
Global solar panel prices down 18% this year
Actions to seize it
- Renegotiate the second panel batch
- Add a fourth array to the installation scope
2 / 2
Opportunity
More installed capacity at the Qalamoun field within the same allocation
A quote under SYP 1,050 per watt
Fallback
If prices rise again, keep to the original scope
Benefit
2 MW more and about SYP 130M a year more in generation-fuel savings
Assessment
The level before and after the response
Inherent
Residual
Potential value
SYP 130M
Residual
No reduction expected — the response is to accept
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 3 days ago · Outside the engine — below «high»
Project manager
Current levelEng. Rami Youssef
Currently followed up here- 2
Programme manager
Eng. Rami Youssef
- 3
PMO director
Dr. Reem Al-Qabbani
- 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Actions to seize the opportunity, with owners and dates
Renegotiate the second panel batch
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syIn progressIn 33 days2026-11-30Add a fourth array to the installation scope
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syNot startedIn 53 days2026-12-20
Trigger
A quote under SYP 1,050 per watt
Fallback
If prices rise again, keep to the original scope
Opportunity strategy
§26 — choose how you will seize it