Corrective plans for serious delay: actions, owners, dates, approval and follow-up, and the projects that need one.
this year, in your scope
followed weekly
or sent back
projects without a plan the rule asks for
past their dates
across the plans
When a corrective plan is required
An active project needs a corrective plan when its forecast finish is more than 40 days past the baseline, or its schedule performance index (SPI) falls below 0.85.
Slip past the baseline
> 40
Schedule performance index
< 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
The rule applies and no plan has been prepared yet.
Corrective plan requiredOff track
Darayya Replacement Housing74 days lateSPI 0.82Eng. Qasem Al-Hariri
Corrective plan requiredOff track
Sheikh Najjar Industrial City Rehabilitation95 days lateSPI 0.78Eng. Youssef Shehabi
Corrective plan requiredAt risk
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals45 days lateSPI 0.88Eng. Maher Al-Hamawi
The plan, its status, what triggered it, its actions, the days won back and its approval.
Display options
| Owner | Next step | ||||||
|---|---|---|---|---|---|---|---|
CP-2026-01 · Version 2 Unified Government e-Services Platform | Awaiting approval | 48 days lateSPI 0.85 | 1 of 6 doneOverdue: 1 | 6 of 21 | 2027-05-12 | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy | Programme manager · Eng. Lina Al-Attar |
CP-2026-02 · Version 1 Aleppo 230 kV Substations Rehabilitation | Approved — under way | 104 days lateSPI 0.76 | 1 of 5 doneOverdue: 1 | 0 of 45 | 2027-02-03 | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy | — |
CP-2026-03 · Version 1 Hama National Hospital Upgrade & Extension | Awaiting approval | 131 days lateSPI 0.72 | 0 of 4 doneOverdue: 1 | 0 of 60 | 2027-06-01 | Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy | National Project Management Office · Dr. Reem Al-Qabbani |
CP-2026-04 · Version 1 Douma Wastewater Treatment Plant | Approved — under way | 55 days lateSPI 0.83 | 1 of 5 done | 0 of 33 | 2027-08-03 | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | — |
CP-2026-05 · Version 1 Integrated Public Financial Management System — Phase 1 | Sent back | 52 days lateSPI 0.83 | 1 of 4 done | 10 of 32 | 2027-02-27 | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy | Project Approval Committee · Dr. Reem Al-Qabbani |