CP-2026-02Version ⁦1⁩

Aleppo 230 kV Substations Rehabilitation

Approved — under wayCriticalOverdue: ⁦1⁩

One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.

What triggered the plan

The project’s reading the day the rule fired, and today.

Detected on ⁦2026-09-01⁩

Slip past the baseline

At detection
104 days
Today
126 days
Limit
> 40

Schedule performance index

At detection
0.76
Today
0.74
Limit
< 0.85

A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.

Days won back

The forecast finish without the plan, with it, and the difference.

  1. Baseline

    2026-09-30
  2. Without the plan

    2027-03-20

    +171 days

  3. With the plan

    2027-02-03

    +126 days

Wins back 45 days

Achieved so far: 0 days

Why it slipped

The main contractor’s cash-flow distress and unpaid subcontractors, an oil leak in substation 2’s transformer during testing, and control-room changes never shown to Civil Defence

Corrective actions

Each action with its owner, date, status and the days it wins back; overdue ones are shaded.

⁦1⁩ of ⁦5⁩ done
  • An executive task force on the contractor’s distress

    Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
    Done2026-09-222026-09-22
  • Appoint an independent financial adviser to audit contractor liquidity

    Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syACT-0307
    Overdue8 days overdue2026-10-20Wins back 10 days
  • Pay subcontractors directly from the next certificate

    Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syACT-0308
    Not startedIn 8 days2026-11-05Wins back 20 days
  • Re-test the transformer after replacing the gaskets

    Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syACT-0309
    In progressIn 5 days2026-11-02Wins back 5 days
  • An early review of the fire and evacuation drawings with the Syrian Civil Defence

    Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy
    In progressIn 18 days2026-11-15Wins back 10 days

Follow-up

The project’s readings after the plan was approved, with the PMO’s notes.

  1. 2026-10-27Dr. Reem Al-Qabbani126 days lateSPI ⁦0.74⁩

    Labour stopped for four days; direct payment raised to the Executive Council (ESC-2026-021)

  2. 2026-10-13Kinan Azzam118 days lateSPI ⁦0.75⁩

    The financial adviser is still not appointed (conflict of interest); re-tendering