CP-2026-02Version 1
Aleppo 230 kV Substations Rehabilitation
One corrective plan: why the project slipped, the rule that triggered it, the actions, the days won back, approval and follow-up.
What triggered the plan
The project’s reading the day the rule fired, and today.
Detected on 2026-09-01
Slip past the baseline
- At detection
- 104 days
- Today
- 126 days
- Limit
- > 40
Schedule performance index
- At detection
- 0.76
- Today
- 0.74
- Limit
- < 0.85
A rule approved by the Project Approval Committee (PMO-2026/14), read automatically from the project’s data.
Days won back
The forecast finish without the plan, with it, and the difference.
Baseline
2026-09-30Without the plan
2027-03-20+171 days
With the plan
2027-02-03+126 days
Wins back 45 days
Achieved so far: 0 days
Why it slipped
The main contractor’s cash-flow distress and unpaid subcontractors, an oil leak in substation 2’s transformer during testing, and control-room changes never shown to Civil Defence
Corrective actions
Each action with its owner, date, status and the days it wins back; overdue ones are shaded.
An executive task force on the contractor’s distress
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syDone2026-09-222026-09-22Appoint an independent financial adviser to audit contractor liquidity
Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syACT-0307Overdue8 days overdue2026-10-20Wins back 10 daysPay subcontractors directly from the next certificate
Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syACT-0308Not startedIn 8 days2026-11-05Wins back 20 daysRe-test the transformer after replacing the gaskets
Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syACT-0309In progressIn 5 days2026-11-02Wins back 5 daysAn early review of the fire and evacuation drawings with the Syrian Civil Defence
Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.syIn progressIn 18 days2026-11-15Wins back 10 days
Follow-up
The project’s readings after the plan was approved, with the PMO’s notes.
2026-10-27Dr. Reem Al-Qabbani126 days lateSPI 0.74
Labour stopped for four days; direct payment raised to the Executive Council (ESC-2026-021)
2026-10-13Kinan Azzam118 days lateSPI 0.75
The financial adviser is still not appointed (conflict of interest); re-tendering