PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦95%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.74⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦68% done against 92% planned⁩.

⁦SPI 0⁩.⁦74⁩, ⁦CPI 0⁩.⁦84⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.1Rehabilitate core energy, water and transport infrastructure

Main initiative

SI-2.1.2Power & water systems rehabilitation

Contribution to the initiative⁦86%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

Annual work-plan line
WP-2024-004
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦68%⁩

Awaiting acceptance ⁦9%⁩

Not handed in ⁦23%⁩

8 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Supply⁦11%⁩
  • Detailed design⁦6%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Installation⁦9%⁩

Corrective planCP-2026-02

Approved — under wayOverdue: ⁦1⁩

The main contractor’s cash-flow distress and unpaid subcontractors, an oil leak in substation 2’s transformer during testing, and control-room changes never shown to Civil Defence

Actions

⁦1⁩ of ⁦5⁩ done

Next: Appoint an independent financial adviser to audit contractor liquidity · Omar Al-Nahhas · 2026-10-20

Days won back

⁦0⁩ of ⁦45⁩

With the plan: 2027-02-03

Open the plan

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦98%⁩ of budget

SYP8.3B/ SYP10.3BSYP2Bprojected overrun(⁦19.0%⁩)
Actual spend
SYP8.3B
Committed
SYP10.1B
Approved budget
SYP10.3B
Estimate at completion
SYP12.3B

Next milestones

  • Closure⁦2027-02-03⁩was ⁦2026-09-30⁩Late

Waiting on someone

⁦1⁩ approval and ⁦3⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦3⁩ open

  • Appoint an independent financial adviser to audit the contractor’s liquidityOmar Al-Nahhas8 days overdue2026-10-20Critical
  • Pay subcontractors directly from the next certificateRasha Al-MudarresIn 8 days2026-11-05Critical
  • ⁦Re-test the station 2 transformer after the leak repair⁩Eng. Maher Al-HamawiIn 5 days2026-11-02High

Risks & impediments

3 open risks, exposure SYP 1.3B

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩1Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩RSK-0021Main contractor cash-flow trouble and late payment of subcontractors
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩1Probability: Possible · Impact: MajorMedium · Score ⁦12⁩RSK-0023Faults in the new transformers during commissioning1Probability: Possible · Impact: SevereHigh · Score ⁦15⁩RSK-0022Control-room fire systems not meeting civil-defence requirements
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical1
  • High1
  • Medium1
  • Low0

Deliverables

⁦8⁩ of ⁦12⁩ approved

  • Project plan & baseline004-D1 · V1 · CRT-004-01⁦3%⁩Eng. Maher Al-Hamawi2024-05-192024-05-19Approved
  • Monitoring & reporting004-D2 · V1 · CRT-004-02⁦3%⁩Eng. Wassim Al-Azm2024-08-052024-08-05Approved
  • Detailed design004-D3 · V1 · CRT-004-03⁦6%⁩Eng. Wassim Al-Azm2024-10-232024-10-23Approved
  • Permits & approvals004-D4 · V1 · CRT-004-04⁦6%⁩Salma Al-Zaim2025-01-092025-01-09Approved
  • Site works & excavation004-D5 · V1 · CRT-004-05⁦13%⁩Salma Al-Zaim2025-03-292025-03-29Approved
  • Structure004-D6 · V1 · CRT-004-06⁦13%⁩Eng. Maher Al-Hamawi2025-06-162025-06-16Approved
  • Finishes004-D7 · V1 · CRT-004-07⁦13%⁩Eng. Wassim Al-Azm2025-09-022025-09-02Approved
  • Supply004-D8 · V1 · CRT-004-08⁦11%⁩Eng. Maher Al-Hamawi2025-11-202025-11-20Approved
  • Installation004-D9 · V1⁦9%⁩Eng. Wassim Al-Azm264 days overdue2026-02-06Submitted
  • Testing & commissioning004-D10 · V0⁦9%⁩Salma Al-Zaim185 days overdue2026-04-26Draft
  • Provisional acceptance004-D11 · V0⁦7%⁩Eng. Wassim Al-Azm107 days overdue2026-07-13Draft
  • Final acceptance004-D12 · V0⁦7%⁩Salma Al-Zaim28 days overdue2026-09-30Draft

Team, contracts & documents

Team

4 members

Eng. Maher Al-Hamawi · Director, Energy, Water & Utilities ProjectsEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upHuda Al-Dandal · Senior Financial Analyst — Investment Plan
  • Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsProject managerP-021maher.alhamawi@psa.gov.sy⁦70%⁩
  • Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upFollow-up lead — substations’ readiness to energiseP-010abdulrahman.alkilani@psa.gov.sy⁦20%⁩
  • Huda Al-DandalHuda Al-DandalSenior Financial Analyst — Investment PlanFinancial analystP-037huda.aldandal@psa.gov.sy⁦15%⁩