PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP10B⁦17⁩ elements
Unallocated contingencySYP309MSYP 515M
Budget at completionSYP10.3BPRJ-2026-004
Weighted progress⁦68%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project1,149⁦2024-01-14⁩⁦2027-03-08⁩⁦68%⁩9,991.008,338.10—
1
Phase308⁦2024-01-14⁩⁦2024-11-17⁩⁦100%⁩599.46735.71—
1.1
WBS element189⁦2024-01-14⁩⁦2024-07-21⁩⁦100%⁩299.73367.860 / 1
1.2
WBS element190⁦2024-05-11⁩⁦2024-11-17⁩⁦100%⁩299.73367.861 / 2
2
Phase307⁦2024-09-07⁩⁦2025-07-11⁩⁦100%⁩1,198.921,471.43—
2.1
WBS element189⁦2024-09-07⁩⁦2025-03-15⁩⁦100%⁩599.46735.711 / 1
2.2
WBS element189⁦2025-01-03⁩⁦2025-07-11⁩⁦100%⁩599.46735.711 / 2
3
Phase426⁦2025-05-01⁩⁦2026-07-01⁩⁦100%⁩3,796.584,659.52—
3.1
WBS element190⁦2025-05-01⁩⁦2025-11-07⁩⁦100%⁩1,265.531,553.171 / 1
3.2
WBS element189⁦2025-08-28⁩⁦2026-03-05⁩⁦100%⁩1,265.531,553.171 / 1
3.3
WBS element189⁦2025-12-24⁩⁦2026-07-01⁩⁦100%⁩1,265.531,553.171 / 2
4
Phase500⁦2025-10-04⁩⁦2027-02-16⁩⁦40%⁩2,997.301,471.43—
4.1
WBS element188⁦2026-04-21⁩⁦2026-10-26⁩⁦100%⁩999.101,226.191 / 1
4.2
WBS element490⁦2025-10-04⁩⁦2027-02-06⁩⁦20%⁩999.10245.241 / 1
4.3
WBS element16⁦2027-01-31⁩⁦2027-02-16⁩⁦0%⁩999.10—1 / 2
5
Phase26⁦2027-02-10⁩⁦2027-03-08⁩⁦0%⁩1,398.74——
5.1
WBS element16⁦2027-02-10⁩⁦2027-02-26⁩⁦0%⁩699.37—1 / 1
5.2
WBS element16⁦2027-02-20⁩⁦2027-03-08⁩⁦0%⁩699.37—1 / 1
Total⁦68%⁩9,991.008,338.10