PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy
Aleppo 230 kV Substations Rehabilitation
Remove from watchlistRehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.
Project managerEng. Maher Al-HamawiProject sponsorSalma Al-ZaimProgrammeEnergy & Water Systems Rehabilitation Programme
Early warning: 95% chance of slipping within 30 days
Budget (BAC)
SYP 10.3B
Actual cost
SYP 8.3B
81% of budget
Progress
68%Awaiting acceptance 9%
Estimate at completion
SYP 12.3B
+SYP 2B
SPI · CPI
0.74Schedule performance index · 0.740.84Cost performance index · 0.84
Forecast finish
2027-02-03
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Period
October 2026
In approvalDue todayAction time limit about to lapse · Limit 2 working days
- Progress
- 68%
- Planned
- 92%
- SPI
- 0.74
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-004-2026-10 | In approval | 68% | Methodology reviewDr. Reem Al-QabbaniDue todayAction time limit about to lapse · Limit 2 working days | 2026-10-26 |
| September 2026UPD-004-2026-09 | Approved | 64% | — | 2026-10-02 |
| August 2026UPD-004-2026-08 | Approved | 60% | — | 2026-09-02 |