PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy

Aleppo 230 kV Substations Rehabilitation

Remove from watchlist

Rehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 10.3B

Actual cost

SYP 8.3B

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SYP 12.3B

+SYP 2B

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
0On track
0At risk
2Late
Average delay209 days
Oct 24Jan 25Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27
Contractual
Build completePlanned: ⁦2025-09-02⁩Forecast / actual: ⁦2026-07-01⁩Delay: 302 daysG3 +302
Executive
Project plan approvedPlanned: ⁦2024-08-05⁩Forecast / actual: ⁦2024-11-17⁩Delay: 104 daysG1 +104
Payment
Final handoverPlanned: ⁦2026-09-30⁩Forecast / actual: ⁦2027-03-08⁩Delay: 159 daysG5 +159
Regulatory
Testing & acceptance completePlanned: ⁦2026-04-26⁩Forecast / actual: ⁦2027-02-16⁩Delay: 296 daysG4 +296
Project
Designs approvedPlanned: ⁦2025-01-09⁩Forecast / actual: ⁦2025-07-11⁩Delay: 183 daysG2 +183

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2024-08-05⁩⁦2024-11-17⁩⁦+104⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-01-09⁩⁦2025-07-11⁩⁦+183⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2025-09-02⁩⁦2026-07-01⁩⁦+302⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-04-26⁩⁦2027-02-16⁩⁦+296⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syLate0Not requested
Final handoverMS-G5Payment⁦2026-09-30⁩⁦2027-03-08⁩⁦+159⁩ daysEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syLate0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦68%⁩

Awaiting acceptance

⁦9%⁩

Not handed in

⁦23%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline004-D1⁦3%⁩CRT-004-01ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2024-05-19⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting004-D2⁦3%⁩CRT-004-02ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2024-08-05⁩V1⁦3⁩ of ⁦3⁩
Detailed design004-D3⁦6%⁩CRT-004-03ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2024-10-23⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals004-D4⁦6%⁩CRT-004-04ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2025-01-09⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation004-D5⁦13%⁩CRT-004-05ApprovedSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2025-03-29⁩V1⁦3⁩ of ⁦3⁩
Structure004-D6⁦13%⁩CRT-004-06ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2025-06-16⁩V1⁦3⁩ of ⁦3⁩
Finishes004-D7⁦13%⁩CRT-004-07ApprovedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2025-09-02⁩V1⁦3⁩ of ⁦3⁩
Supply004-D8⁦11%⁩CRT-004-08ApprovedEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.syEng. Wassim Al-Azm⁦2025-11-20⁩V1⁦3⁩ of ⁦3⁩
Installation004-D9⁦9%⁩—SubmittedEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-02-06⁩V1⁦1⁩ of ⁦3⁩
Testing & commissioning004-D10⁦9%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-04-26⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance004-D11⁦7%⁩—DraftEng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syEng. Wassim Al-Azm⁦2026-07-13⁩V0⁦0⁩ of ⁦3⁩
Final acceptance004-D12⁦7%⁩—DraftSalma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.syEng. Wassim Al-Azm⁦2026-09-30⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩