PRJ-2026-004Critical4ExecutionConstructionStalledDelivered by:Ministry of Energy
Aleppo 230 kV Substations Rehabilitation
Remove from watchlistRehabilitating four 230 kV substations in Aleppo city (28 high-voltage bays) and linking them to the control centre, to lengthen supply hours in the neighbourhoods and the industrial zone.
Project managerEng. Maher Al-HamawiProject sponsorSalma Al-ZaimProgrammeEnergy & Water Systems Rehabilitation Programme
Early warning: 95% chance of slipping within 30 days
Budget (BAC)
SYP 10.3B
Actual cost
SYP 8.3B
81% of budget
Progress
68%Awaiting acceptance 9%
Estimate at completion
SYP 12.3B
+SYP 2B
SPI · CPI
0.74Schedule performance index · 0.740.84Cost performance index · 0.84
Forecast finish
2027-02-03
126 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure13 July 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started