PMO Command Centre
The enterprise view of the portfolio: status, performance, early warning, escalations, decisions and data quality.
- Total projects
- 36
- Weighted progress
- 52%−5%
- SPI
- 0.85−0.04
- CPI
- 0.93−0.02
- Open high risks
- 18
SYP 129.3B
Planned 57%
Schedule performance (SPI)
Cost performance (CPI)
of 45 open risks
Pick a status to filter the map and lists
Portfolio performance
The six portfolios by health score, forecast cost and the two performance indices, with the project map by risk and value.
Portfolio map: risk × strategic value
Bubble size = budget. Pick a project to drill down.
- On track
- At risk
- Off track
- Critical
- On hold
Portfolio board
Pick a portfolio to drill into its programmes and projects.
| Portfolio | Health score | Estimate at completion | SPI | CPI | Status mix |
|---|---|---|---|---|---|
| 7 projects | SYP 5.1B | 0.92Schedule performance index · 0.92 | 0.98Cost performance index · 0.98 | ||
| 4 projects | SYP 36.8B | 0.79Schedule performance index · 0.79 | 0.88Cost performance index · 0.88 | ||
| 7 projects | SYP 9.4B | 0.91Schedule performance index · 0.91 | 0.94Cost performance index · 0.94 | ||
| 5 projects | SYP 18.2B | 0.83Schedule performance index · 0.83 | 0.90Cost performance index · 0.90 | ||
| 8 projects | SYP 69.3B | 0.87Schedule performance index · 0.87 | 0.95Cost performance index · 0.95 | ||
| 5 projects | SYP 762.3M | 0.98Schedule performance index · 0.98 | 1.00Cost performance index · 1.00 |
Early warning and escalations
The early-warning engine reads the SPI trend, the task-closure rate and the open risks; whatever breaks a threshold reaches the escalation queue.
Slip forecasts
16 projects with a 35%+ chance of slipping
- 97%
Critical today, but a 97% chance of slipping within 30 days.
CriticalSPI0.70Schedule performance index · 0.70Schedule variance: 30.5% - 95%
Critical today, but a 95% chance of slipping within 30 days.
CriticalSPI0.74Schedule performance index · 0.74Schedule variance: 26.1% - 88%
Off track today, but a 88% chance of slipping within 60 days.
Off trackSPI0.82Schedule performance index · 0.82Schedule variance: 17.6% - 86%
Off track today, but a 86% chance of slipping within 30 days.
Off trackSPI0.82Schedule performance index · 0.82Schedule variance: 17.6% - 84%
Off track today, but a 84% chance of slipping within 45 days.
Off trackSPI0.78Schedule performance index · 0.78Schedule variance: 22.0% - 81%
Off track today, but a 81% chance of slipping within 60 days.
Off trackSPI0.80Schedule performance index · 0.80Schedule variance: 20.0% - 74%
At risk today, but a 74% chance of slipping within 45 days.
At riskSPI0.87Schedule performance index · 0.87Schedule variance: 13.4%
Escalation queue
What crossed a variance threshold or an action time limit, and who is handling it.
- ESC-2026-031Schedule varianceExecutive CouncilBeing handled
Schedule variance 31%; forecast 152 days past baseline
Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy2026-10-0540 hours overdueAction time limit exceeded - ESC-2026-032Critical riskExecutive CouncilOpen
Critical risk (25): main-contractor cash distress, subcontractors idle
Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy2026-10-1922 hours leftAction time limit about to lapse - ESC-2026-033Schedule variancePMOOpen
Schedule variance 18% from the late land hand-over in blocks 3 and 4
Dr. Reem Al-QabbaniDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.sy2026-10-2130 hours leftAction time limit about to lapse - ESC-2026-034Action time limit passedPMOBeing handled
The integration-engineer impediment is three days past its action time limit
Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004lina.alattar@psa.gov.sy2026-10-2218 hours leftAction time limit about to lapse - ESC-2026-035Cost overrunPMOOpen
The ground-improvement variation pushes EAC SYP 565M past contingency
Dr. Reem Al-QabbaniDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.sy2026-10-243 days leftWithin the time limit - ESC-2026-036Critical riskPMOOpen
Unforeseen ground needs the foundations of five axes redesigned
Dr. Reem Al-QabbaniDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.sy2026-10-264 days leftWithin the time limit
Budget, forecast and risk
The forecast-cost trend with a confidence band to year end, and the map of open risks.
Estimate at completion
Actual to October, then forecast with a confidence band · axis in SYP billions · Estimate at completion
- EAC
- Approved budget
- Forecast
- Forecast range
Open-risk map
45 risks · pick a cell to list its risks
- Critical6
- High12
- Medium24
- Low3
- Risks 45
Impact
Highest-scoring risks
- 16Civil-registry identity and interoperability interfaces not ready on timeSYP 60M
- 16Shortage of integration and back-end engineers on the vendor teamSYP 46.3M
- 16Customisation and ministry-systems integration cost above the approved reserveSYP 170M
- 20Steel and concrete price rises driving price-adjustment claimsSYP 1.2B
- 20Late hand-over of the northern plot and utility diversions in blocks 3 and 4SYP 775M
Strategic alignment and benefits
How much of the budget serves the development framework’s objectives, and how much benefit has actually landed.
Budget by objective and portfolio
A project linked to two objectives counts in both · Budget (SYP bn)
Average alignment score
83
out of 100
Strongly aligned budget
77%
Projects scoring 80+ on alignment
Objectives served
11 / 12
of the 2026–2030 framework’s objectives
Benefits realised by portfolio
Planned to date against realised · SYP bn
- Planned to date
- Realised
Decisions needed
What waits for a committee or the President, by action time limit.
Waiting for a decision
15 decisions
- 6 days overdueAction time limit exceededHama National Hospital 150-day extension
Change request · Hama National Hospital Upgrade & Extension
- 26 hours overdueAction time limit exceeded
- 18 hours leftAction time limit about to lapseRule on the escalated impediment — integration engineers withdrawn
Decision · Unified Government e-Services Platform
- 20 hours leftAction time limit about to lapseAdd civil-record transfer & record merge
Change request · Unified Government e-Services Platform
- 22 hours leftAction time limit about to lapseDirect payment to subcontractors on the Aleppo substations
Decision · Aleppo 230 kV Substations Rehabilitation
- 44 hours leftAction time limit about to lapsePublic financial management system customisation allocation increase
Budget · Integrated Public Financial Management System — Phase 1
- 2 days leftAction time limit about to lapseDecide on taking the Hama hospital claims to the dispute committee
Decision · Hama National Hospital Upgrade & Extension
- 4 days leftWithin the time limitApprove the updated corrective plan for the unified e-services platform
Approval · Unified Government e-Services Platform
- 4 days leftWithin the time limitApprove the change request for extra integration capacity on the e-services platform
Change request · Unified Government e-Services Platform
- 5 days leftWithin the time limit
- 6 days leftWithin the time limitReview the public financial management system re-baseline
Gate review · Integrated Public Financial Management System — Phase 1
- 7 days leftWithin the time limitProvisional acceptance readiness — Madinat al-Salam water network
Gate review · Madinat al-Salam Drinking-Water Network (Quneitra)
- 7 days leftWithin the time limitAccept a deliverable: the wave 1 service package (24 services)
Approval · Unified Government e-Services Platform
- 13 days leftWithin the time limitApprove the plan tracker charter before the initiation gate
Gate review · Medium-Term Plan Implementation Tracker (ministries & governorates)
- 28 days leftWithin the time limitVerify the conditions on the plan tracker gate
Gate review · Medium-Term Plan Implementation Tracker (ministries & governorates)
The President’s list
Decisions raised to the President and the Executive Council, and where they stand now.
- Pay subcontractors directly on the Aleppo 230 kV substations rehabilitationAwaiting decision
- Refer the Hama National Hospital contractor’s claims to arbitrationAwaiting decision
- Approve the updated corrective plan for the Unified Government e-Services PlatformAwaiting decision
- Release SYP 550M of the Reconstruction & Infrastructure portfolio reserve to speed up the Darayya housing land hand-overAwaiting decision
- Approve the October National Steering Committee minutesAwaiting decision
Compliance and data quality
A composite score per project manager: data quality 45%, mandatory documents complete 35%, update freshness 20%.
Leaders
The five most compliant project managers
- 1Eng. Hussam ZeidanDirector, CybersecurityEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy96Data quality95%Documents97%Freshness97%
1 project
- 2Rana Al-SammanHead of National StrategyRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy95Data quality94%Documents96%Freshness97%
1 project
- 3Nizar Abu FakhrHead, Monitoring, Evaluation & PerformanceNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy93Data quality97%Documents99%Freshness78%
2 projects
- 4Eng. Qasem Al-HaririDirector, Transport & Housing ProjectsEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy90Data quality90%Documents89%Freshness91%
2 projects
- 5Kinan AzzamSenior Digital Delivery Consultant — National PMOKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy90Data quality93%Documents95%Freshness74%
3 projects
Laggards
They need support from the PMO
- 1Mariam Al-ZoubiDirector, Education & Rural Development ProjectsMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy68Data quality78%Documents79%Freshness31%
2 projects
- 2Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy69Data quality75%Documents78%Freshness43%
2 projects
- 3Eng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy70Data quality76%Documents72%Freshness54%
2 projects
- 4Eng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy72Data quality75%Documents75%Freshness58%
3 projects
- 5Eng. George HaddadDirector, Data Centres & Government NetworkEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy74Data quality78%Documents78%Freshness56%
4 projects
Late updates
4 active projects not updated for more than 14 days
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Last update 56 days ago · Data quality 58%
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals
Last update 44 days ago · Data quality 54%
Government Fibre Backbone — Damascus–Homs Segment
Last update 37 days ago · Data quality 61%
Hasakah Wheat Digital Crop Survey
Last update 34 days ago · Data quality 66%