CR-2026-008Integrated Public Financial Management System — Phase 1

Increase the customisation & integration budget

BudgetIn reviewImpact level: MajorIn 2 days2026-10-30

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 170M

Current budgetSYP 1.6B

After the changeSYP 1.8B

+10.5%

Schedule

+⁦45⁩ d
  • Baseline finish2026-12-31
  • New finish2027-02-14

Benefits

+3%

Month-end close in 5 days instead of 12

⁦+3⁩% of expected benefits

Reason for change

Customisations and the ministries’ payroll and e-payment integration missed in the tender book

Justification

Without them the financial module cannot go live and payroll and fees stay reconciled by hand in the ministries

PMO recommendation

Approve with conditions

The national PMO recommends approval after the independent estimate review

Conditions

  • The independent estimate review before signature

Approval workflow

  1. Submitted

    Nour Al-Jabiri

    Done2026-10-09

  2. PM review

    Nour Al-Jabiri

    Done2026-10-10

  3. Impact analysis

    Kinan Azzam

    Done2026-10-14

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-10-15

  5. 5

    Change committee recommendation

    Dr. Ziad Al-Atassi

    Now2026-10-29

  6. 6

    Executive Council decision

    Dr. Samer Al-Daqqar

    Later

  7. 7

    Baseline updated

    Nour Al-Jabiri

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SYP 125M or 90 days

  • A cost impact of SYP 170M is above SYP 125M — «major»: the Change Committee recommends and the Executive Council decides.
  • It has a financial link, so Finance & Procurement take part before the decision.

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

Change Committee — meeting 4229 October 2026 13:00Meeting room 3 — fifth floor
  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairNot voted
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouNot voted
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syApprove with conditions
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syNot voted
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syNot voted
2/6⁦2⁩ short of quorum
  • Approve1
  • Approve with conditions1
  • Reject0
  • Abstain0

⁦2⁩ short of quorum · Awaiting the change committee’s decision in meeting ⁦42⁩