Projects

The project register by code, name, sector, classification, status, stage, year and owner.

Working on:Planning and Statistics Authority
Projects in scope
36

25 in progress

Approved budget
SYP 129.3B

Forecast at completion SYP 139.5B

Stalled projects
6

plus ⁦10⁩ at risk

On the watchlist
7

Followed closely by leadership

Try:

Project statuses

The Authority’s six statuses, derived automatically from the stage, the health and status decisions — pick one to filter the register

⁦36⁩ results
Export CSV
Add to watchlist
PRJ-2026-026StoppedOperationalProjects Follow-up2026WP-2026-026On hold3Planning⁦8%⁩SYP825MSYP825M0.89Schedule performance index · 0.891.00Cost performance index · 1.00⁦2027-10-31⁩123 days late1Data quality · GoodEng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy
Add to watchlist
Al-Mayadin General Hospital
Health, Education & Industrial Recovery Portfolio
PRJ-2026-033StoppedStrategicProjects Follow-up2026WP-2026-033On hold3Planning⁦2%⁩SYP5.3BSYP5.3B1.00Schedule performance index · 1.001.00Cost performance index · 1.00⁦2028-12-31⁩184 days late1Data quality · ExcellentEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy
Remove from watchlist
PRJ-2026-004StalledOperationalProjects Follow-up2024WP-2024-004Critical4Execution⁦68%⁩SYP10.3BSYP12.3BSYP−2B0.74Schedule performance index · 0.740.84Cost performance index · 0.84⁦2027-02-03⁩126 days late3Data quality · GoodEng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy
Remove from watchlist
Hama National Hospital Upgrade & Extension
Health, Education & Industrial Recovery Portfolio
PRJ-2026-007StalledStrategicProjects Follow-up2024WP-2024-007Critical4Execution⁦57%⁩SYP16BSYP19.5BSYP−3.5B0.70Schedule performance index · 0.700.82Cost performance index · 0.82⁦2027-06-01⁩152 days late3Data quality · GoodEng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy
Remove from watchlist
Integrated Public Financial Management System — Phase 1
Government Digital Infrastructure & Systems Portfolio
PRJ-2026-001StalledOperationalDigital2025WP-2025-001Off track4Execution⁦61%⁩SYP1.6BSYP1.8BSYP−219.9M0.82Schedule performance index · 0.820.88Cost performance index · 0.88⁦2027-02-27⁩58 days late3Data quality · ExcellentNour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy
Remove from watchlist
Darayya Replacement Housing
Reconstruction & Infrastructure PortfolioCorrective plan required
PRJ-2026-002StalledStrategicProjects Follow-up2024WP-2024-002Off track4Execution⁦42%⁩SYP29.5BSYP31.7BSYP−2.2B0.82Schedule performance index · 0.820.93Cost performance index · 0.93⁦2027-09-12⁩74 days late4Data quality · ExcellentEng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
Remove from watchlist
Sheikh Najjar Industrial City Rehabilitation
Health, Education & Industrial Recovery PortfolioCorrective plan required
PRJ-2026-006StalledStrategicLocal Development2024WP-2024-006Off track4Execution⁦39%⁩SYP7.2BSYP8BSYP−883.7M0.78Schedule performance index · 0.780.89Cost performance index · 0.89⁦2027-07-04⁩95 days late2Data quality · ExcellentEng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy
Remove from watchlist
Douma Wastewater Treatment Plant
Reconstruction & Infrastructure Portfolio
PRJ-2026-020StalledStrategicProjects Follow-up2024WP-2024-020Off track4Execution⁦44%⁩SYP8.6BSYP9.1BSYP−453.9M0.80Schedule performance index · 0.800.95Cost performance index · 0.95⁦2027-08-03⁩64 days late2Data quality · ExcellentEng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
Add to watchlist
Government Backup Data Centre, Homs — Phase 2
Government Digital Infrastructure & Systems Portfolio
PRJ-2026-003In progressOperationalDigital2025WP-2025-003At risk4Execution⁦72%⁩SYP3.7BSYP4.1BSYP−365.9M0.90Schedule performance index · 0.900.91Cost performance index · 0.91⁦2027-01-07⁩38 days late2Data quality · ExcellentEng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy
Add to watchlist
Government Cloud & Ministry Systems Migration
Government Digital Infrastructure & Systems Portfolio
PRJ-2026-009In progressOperationalDigital2025WP-2025-009At risk4Execution⁦47%⁩SYP1.3BSYP1.3BSYP−40.2M0.89Schedule performance index · 0.890.97Cost performance index · 0.97⁦2027-03-21⁩21 days late1Data quality · ExcellentEng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy
Total · 36SYP129.3BSYP139.5B