PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−14

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦2% done against 2% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Human DevelopmentSO-3.1Better access to health and education

Main initiative

Under no initiative — listed under «projects with no strategic link»

Secondary links

Annual work-plan line
WP-2026-033
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦2%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦98%⁩

1 deliverable accepted

  • Project plan & baseline⁦2%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦2⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦2%⁩ of budget

    SYP105M/ SYP5.3B
    Actual spend
    SYP105M
    Committed
    SYP115M
    Approved budget
    SYP5.3B
    Estimate at completion
    SYP5.3B

    Next milestones

    • 50% of works complete⁦2027-08-10⁩was ⁦2027-05-10⁩Late
    • Provisional acceptance⁦2028-09-08⁩was ⁦2028-04-23⁩Late
    • Closure⁦2028-12-31⁩was ⁦2028-06-30⁩Late

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    1 open risk, exposure SYP 300M

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0044Late land allocation and registration by the Deir ez-Zor governorate councilProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical1
    • High0
    • Medium0
    • Low0

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦12⁩ approved

    • Project plan & baseline033-D1 · V1 · CRT-033-01⁦2%⁩Eng. Sara Al-Barazi2026-06-172026-06-17Approved
    • Monitoring & reporting033-D2 · V0⁦3%⁩Eng. Wassim Al-Azm65 days overdue2026-08-24Draft
    • Detailed design033-D3 · V0⁦6%⁩Eng. Wassim Al-AzmIn 2 days2026-10-30Draft
    • Permits & approvals033-D4 · V0⁦6%⁩Eng. Bashir Al-TaiIn 70 days2027-01-06Draft
    • Site works & excavation033-D5 · V0⁦13%⁩Eng. Bashir Al-TaiIn 138 days2027-03-15Draft
    • Structure033-D6 · V0⁦13%⁩Eng. Sara Al-BaraziIn 205 days2027-05-21Draft
    • Finishes033-D7 · V0⁦13%⁩Eng. Wassim Al-AzmIn 273 days2027-07-28Draft
    • Supply033-D8 · V0⁦10%⁩Eng. Sara Al-BaraziIn 341 days2027-10-04Draft
    • Installation033-D9 · V0⁦10%⁩Eng. Wassim Al-AzmIn 408 days2027-12-10Draft
    • Testing & commissioning033-D10 · V0⁦10%⁩Eng. Bashir Al-TaiIn 476 days2028-02-16Draft
    • Provisional acceptance033-D11 · V0⁦7%⁩Eng. Wassim Al-AzmIn 543 days2028-04-23Draft
    • Final acceptance033-D12 · V0⁦7%⁩Eng. Bashir Al-TaiIn 611 days2028-06-30Draft

    Team, contracts & documents

    Team

    1 member

    Eng. Sara Al-Barazi · Senior Project Manager — Hospitals & Health Facilities
    • Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesProject manager (on hold)P-022sara.albarazi@psa.gov.sy⁦10%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house

    Documents

    • No documents yet

    Meetings

    • No meetings scheduled
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close