Planning and Statistics Authority
Project charter
Al-Mayadin General Hospital
1Project identity
Required at this stage- Project name
- Al-Mayadin General Hospital
- Project code
- PRJ-2026-033
- Project sponsor
- Eng. Bashir Al-TaiEng. Bashir Al-TaiDeputy President, Local Development & GovernoratesP-049bashir.altai@psa.gov.sy
- Project manager
- Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy
- Project owner
- Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.sy
- Portfolio & programme
- Health, Education & Industrial Recovery PortfolioPublic Hospitals Rehabilitation Programme
- Type & methodology
- Construction · Construction
- Current phase
- 3Planning
2Background & rationale
Required at this stageA general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.
3Objectives
Required at this stage- 1Better access to health and education
- 2Comparable public-service quality in every governorate
4Scope
Required at this stageIn scope
- A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.
- Syrian Arab Building Code compliance
- Consultant-approved drawings
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
5High-level requirements
Required at this stage- 1Syrian Arab Building Code compliance
- 2Consultant-approved drawings
- 3Health & safety requirements
6Deliverables
Required at this stage| 1 | Project management plan | 2026-04-04 |
| 2 | Main deliverable — stage 1 | 2027-05-10 |
| 3 | Main deliverable — final stage | 2028-03-03 |
| 4 | Final report | 2028-06-30 |
7Key milestones
Required at this stage- Charter approved2026-02-27
- Contract signed2026-07-15
- 50% of works complete2027-05-10
- Provisional acceptance2028-04-23
- Closure2028-06-30
8Budget
Required at this stage- Main contract72.0%SYP3.8B
- Supervision & consulting14.0%SYP735M
- Internal team9.0%SYP472.5M
- Contingency reserve (5%)5.0%SYP262.5M
9Timeline
Required at this stage10Key risks
Required at this stage- HighLate land allocation and registration by the Deir ez-Zor governorate council
11Constraints
Required at this stage- Stay within the approved budget
- Comply with the unified contracts law (Law 51 of 2004)
12Assumptions
Required at this stage- Named internal staff available throughout
- Approvals land within the workflow’s action time limits
13Stakeholders
Required at this stage- Project sponsorDecisions and funding
- Project ownerAccepts deliverables, owns benefits
- National Project Management Office (PMO)Governance and compliance
14Success criteria
Required at this stage- 1Delivered within the approved budget
- 2On the approved date ±5%
- 3Target benefits within 12 months
15Governance structure
Required at this stage- Change CommitteeApproves scope, cost and schedule changesWeekly
- Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
- Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly