PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+189⁩ days vs approved

Baseline (original = approved)⁦2028-06-30⁩
Current forecast⁦2029-01-05⁩
By earned schedule⁦2033-12-09⁩
Critical activities
12
of ⁦17⁩ open activities
Late activities
12
past their baseline finish
Schedule performance
0.10
earned ÷ planned value
Next milestone
in 110 days
Project plan approved
Expand allCollapse all
Activity
Al-Mayadin General HospitalPlanned: ⁦2026-03-01⁩ → ⁦2028-06-30⁩Forecast: ⁦2026-03-01⁩ → ⁦2029-01-05⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-03-01⁩ → ⁦2026-08-24⁩Forecast: ⁦2026-03-01⁩ → ⁦2027-02-15⁩Float: ⁦0⁩d
Project plan & baselinePlanned: ⁦2026-03-01⁩ → ⁦2026-06-17⁩Forecast: ⁦2026-03-01⁩ → ⁦2026-12-03⁩Float: ⁦5⁩dDrag to change its duration+169
Monitoring & reportingPlanned: ⁦2026-05-08⁩ → ⁦2026-08-24⁩Forecast: ⁦2026-10-28⁩ → ⁦2027-02-15⁩Float: ⁦0⁩dDrag to change its dates+175
Project plan approvedPlanned: ⁦2026-08-24⁩ → ⁦2026-08-24⁩Forecast: ⁦2027-02-15⁩ → ⁦2027-02-15⁩Float: ⁦690⁩dDrag to change its datesProject plan approved
Design & permitsPlanned: ⁦2026-07-14⁩ → ⁦2027-01-06⁩Forecast: ⁦2027-01-05⁩ → ⁦2027-07-03⁩Float: ⁦0⁩d
Detailed designPlanned: ⁦2026-07-14⁩ → ⁦2026-10-30⁩Forecast: ⁦2027-01-05⁩ → ⁦2027-04-25⁩Float: ⁦0⁩dDrag to change its dates+177
Permits & approvalsPlanned: ⁦2026-09-20⁩ → ⁦2027-01-06⁩Forecast: ⁦2027-03-15⁩ → ⁦2027-07-03⁩Float: ⁦0⁩dDrag to change its dates+178
Designs approvedPlanned: ⁦2027-01-06⁩ → ⁦2027-01-06⁩Forecast: ⁦2027-07-03⁩ → ⁦2027-07-03⁩Float: ⁦552⁩dDrag to change its datesDesigns approved
Civil worksPlanned: ⁦2026-11-26⁩ → ⁦2027-07-28⁩Forecast: ⁦2027-05-23⁩ → ⁦2028-01-26⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2026-11-26⁩ → ⁦2027-03-15⁩Forecast: ⁦2027-05-23⁩ → ⁦2027-09-10⁩Float: ⁦0⁩dDrag to change its dates+179
StructurePlanned: ⁦2027-02-02⁩ → ⁦2027-05-21⁩Forecast: ⁦2027-07-31⁩ → ⁦2027-11-18⁩Float: ⁦0⁩dDrag to change its dates+181
FinishesPlanned: ⁦2027-04-11⁩ → ⁦2027-07-28⁩Forecast: ⁦2027-10-08⁩ → ⁦2028-01-26⁩Float: ⁦0⁩dDrag to change its dates+182
Build completePlanned: ⁦2027-07-28⁩ → ⁦2027-07-28⁩Forecast: ⁦2028-01-26⁩ → ⁦2028-01-26⁩Float: ⁦345⁩dDrag to change its datesBuild complete
MEP worksPlanned: ⁦2027-06-17⁩ → ⁦2028-02-16⁩Forecast: ⁦2027-12-16⁩ → ⁦2028-08-20⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2027-06-17⁩ → ⁦2027-10-04⁩Forecast: ⁦2027-12-16⁩ → ⁦2028-04-04⁩Float: ⁦0⁩dDrag to change its dates+183
InstallationPlanned: ⁦2027-08-24⁩ → ⁦2027-12-10⁩Forecast: ⁦2028-02-23⁩ → ⁦2028-06-12⁩Float: ⁦0⁩dDrag to change its dates+185
Testing & commissioningPlanned: ⁦2027-10-31⁩ → ⁦2028-02-16⁩Forecast: ⁦2028-05-02⁩ → ⁦2028-08-20⁩Float: ⁦0⁩dDrag to change its dates+186
Testing & acceptance completePlanned: ⁦2028-02-16⁩ → ⁦2028-02-16⁩Forecast: ⁦2028-08-20⁩ → ⁦2028-08-20⁩Float: ⁦138⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2028-01-06⁩ → ⁦2028-06-30⁩Forecast: ⁦2028-07-10⁩ → ⁦2029-01-05⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2028-01-06⁩ → ⁦2028-04-23⁩Forecast: ⁦2028-07-10⁩ → ⁦2028-10-28⁩Float: ⁦0⁩dDrag to change its dates+188
Final acceptancePlanned: ⁦2028-03-14⁩ → ⁦2028-06-30⁩Forecast: ⁦2028-09-17⁩ → ⁦2029-01-05⁩Float: ⁦0⁩dDrag to change its dates+189
Final handoverPlanned: ⁦2028-06-30⁩ → ⁦2028-06-30⁩Forecast: ⁦2029-01-05⁩ → ⁦2029-01-05⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦17⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦11⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦1⁩ more activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Project plan & baseline” needs a pace ⁦3.3⁩× faster than it has kept

It earned ⁦67%⁩ in 241 days; the forecast assumes the rest in 36 days. At the pace so far it finishes on ⁦2027-02-24⁩.

The critical chain

In date order, to final acceptance

Near-critical