PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 5.3B split into spent, committed and left, with the estimate at completion

EAC SYP 5.3B
Revised request SYP 5.3B
  • Actual spendSYP 105M
  • Committed, not spentSYP 10M
  • Allotted, uncommittedSYP 5B
  • Contingency availableSYP 157.5M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 5.3B
Original budgetwhen the first baseline was approved
SYP 5.3B
Approved budgetafter approved change requests
SYP 5.3B
Current budgetavailable to spend now
SYP 5.3B
Revised budgetif the pending changes are approved
SYP 5.3B

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 115M
Contracts0 active contracts
SYP 0
Purchase orders⁦3⁩ orders
SYP 115M
Remaining budgetapproved less actual
SYP 5.1B

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 105M
Accrualswork done, not yet invoiced
SYP 4.2M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 5.3B
ContingencySYP 105M drawn of SYP 262.5M
SYP 157.5M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 5.3B
ApprovedSYP 5.3B
Estimate at completionSYP 5.3B
Approved equals the estimate
The estimate at completion is SYP 0 (⁦0.0%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-12-16⁩

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51033
  • WBS elements⁦5⁩ elements · P-2026-033.01 …
  • Purchase orders⁦2⁩ synced · ⁦1⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 105M drawn of SYP 262.5M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 105M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance305.55105.40105.00308.72⁦−3.17⁩
2Design & permits611.101.230.00620.75⁦−9.65⁩
3Civil works1,935.153.880.001,965.71⁦−30.56⁩
4MEP works1,527.753.060.001,551.87⁦−24.12⁩
5Handover712.951.430.00724.21⁦−11.26⁩
Unallocated contingency157.500.000.0078.75⁦+78.75⁩
Total5,250.00115.00105.005,250.00⁦+0.00⁩

Budget split

WBS

SYP 5.3B

Budget

  • Management & governanceSYP 305.6M⁦6%⁩
  • Design & permitsSYP 611.1M⁦12%⁩
  • Civil worksSYP 1.9B⁦37%⁩
  • MEP worksSYP 1.5B⁦29%⁩
  • HandoverSYP 713M⁦14%⁩
  • Unallocated contingencySYP 157.5M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2033-12-09⁩+1,988

SPI(t) ⁦0.29⁩ against the approved finish ⁦2028-06-30⁩

Planned valuePV
SYP 1B
The value of the work that should be done by today.
PV
Earned valueEV
SYP 105M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 105M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 5.3B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−935.82⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.10
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 5.3B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 5.1B
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 5.3B
  • If the rest goes to planSYP 5.3B
  • At cost and schedule performanceSYP 51.1B
  • The PM’s bottom-up estimateSYP 5.3B
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SYP 5.3B

Variance at completion: ⁦+0.00⁩ SYP M