PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health

Al-Mayadin General Hospital

Add to watchlist

A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.

Budget (BAC)

SYP 5.3B

Actual cost

SYP 105M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 5.3B

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

184 days behind baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution15 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP5.1B⁦17⁩ elements
Unallocated contingencySYP157.5MSYP 262.5M
Budget at completionSYP5.3BPRJ-2026-033
Weighted progress⁦2%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project1,041⁦2026-03-01⁩⁦2029-01-05⁩⁦2%⁩5,092.50105.00—
1
Phase351⁦2026-03-01⁩⁦2027-02-15⁩⁦34%⁩305.55105.00—
1.1
WBS element277⁦2026-03-01⁩⁦2026-12-03⁩⁦67%⁩152.78105.000 / 1
1.2
WBS element110⁦2026-10-28⁩⁦2027-02-15⁩⁦0%⁩152.78—1 / 2
2
Phase179⁦2027-01-05⁩⁦2027-07-03⁩⁦0%⁩611.10——
2.1
WBS element110⁦2027-01-05⁩⁦2027-04-25⁩⁦0%⁩305.55—1 / 1
2.2
WBS element110⁦2027-03-15⁩⁦2027-07-03⁩⁦0%⁩305.55—1 / 2
3
Phase248⁦2027-05-23⁩⁦2028-01-26⁩⁦0%⁩1,935.15——
3.1
WBS element110⁦2027-05-23⁩⁦2027-09-10⁩⁦0%⁩645.05—1 / 1
3.2
WBS element110⁦2027-07-31⁩⁦2027-11-18⁩⁦0%⁩645.05—1 / 1
3.3
WBS element110⁦2027-10-08⁩⁦2028-01-26⁩⁦0%⁩645.05—1 / 2
4
Phase248⁦2027-12-16⁩⁦2028-08-20⁩⁦0%⁩1,527.75——
4.1
WBS element110⁦2027-12-16⁩⁦2028-04-04⁩⁦0%⁩509.25—1 / 1
4.2
WBS element110⁦2028-02-23⁩⁦2028-06-12⁩⁦0%⁩509.25—1 / 1
4.3
WBS element110⁦2028-05-02⁩⁦2028-08-20⁩⁦0%⁩509.25—1 / 2
5
Phase179⁦2028-07-10⁩⁦2029-01-05⁩⁦0%⁩712.95——
5.1
WBS element110⁦2028-07-10⁩⁦2028-10-28⁩⁦0%⁩356.48—1 / 1
5.2
WBS element110⁦2028-09-17⁩⁦2029-01-05⁩⁦0%⁩356.48—1 / 1
Total⁦2%⁩5,092.50105.00