PRJ-2026-033On hold3PlanningConstructionStoppedDelivered by:Ministry of Health
Al-Mayadin General Hospital
Add to watchlist
A general hospital in Al-Mayadin serving the eastern Deir ez-Zor countryside with emergency, surgery, paediatrics and maternity — paused until the governorate council completes the land allocation.
1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Forecast finish
2028-12-31
184 days behind baseline
Planning·Stage 3 of 5
Next gate:Execution15 July 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate1 March 2026Planning · Current stagePlanning · Current stage
Gate into «Execution»DecisionNot held yetDate15 July 2026Execution · Not startedExecution · Not started
Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+189 days vs approved
Baseline (original = approved)2028-06-30
Current forecast2029-01-05
By earned schedule2033-12-09
Critical activities
12
of 17 open activities
Late activities
12
past their baseline finish
Schedule performance
0.10
earned ÷ planned value
Next milestone
in 110 days
Project plan approved
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2026
2027
2028
2029
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
Today
2029-01-052%
Al-Mayadin General HospitalPlanned: 2026-03-01 → 2028-06-30Forecast: 2026-03-01 → 2029-01-05Float: 0d
Project plan & baselinePlanned: 2026-03-01 → 2026-06-17Forecast: 2026-03-01 → 2026-12-03Float: 5dDrag to change its duration+169
2027-02-150%
Monitoring & reportingPlanned: 2026-05-08 → 2026-08-24Forecast: 2026-10-28 → 2027-02-15Float: 0dDrag to change its dates+175
2027-02-150%
Project plan approvedPlanned: 2026-08-24 → 2026-08-24Forecast: 2027-02-15 → 2027-02-15Float: 690dDrag to change its datesProject plan approved