Programme · PG-05 · Health, Education & Industrial Recovery Portfolio

Public Hospitals Rehabilitation Programme

Critical

Upgrading Hama National Hospital and building Al-Mayadin General Hospital.

Approved budget
SYP 21.7B

incl. SYP 450M programme reserve

Actual spend
SYP 11.2B

⁦52%⁩ of budget

EAC
SYP 24.8B+16.5%

Estimate at completion

Progress
⁦31%⁩

Planned ⁦45%⁩

Schedule performance index
0.77

Cost performance index 0.86

Manager

Eng. Sara Al-Barazi

Senior Project Manager — Hospitals & Health Facilities

Sponsor

Salma Al-Zaim

Deputy President, Finance, Administration & the Investment Plan

Projects

2 projects

2024-02-04 — 2028-12-31

Critical 1On hold 1

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Upgrade and extend Hama National Hospital and close its temporary wards by 2028

  2. 2

    A new public hospital in Al-Mayadin serving rural eastern Deir ez-Zor

  3. 3

    A standard ward and theatre design adopted for the new hospitals

Programme benefits

From baseline to target

  • Annual savings from closing temporary wards

    by ⁦2028⁩
    Baseline 0Current 0 SYP bnTarget 1.6
  • Wards moved into permanent buildings

    by ⁦2028⁩
    Baseline 0Current 0 wardsTarget 14

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
20242025202620272028
2027-06-01
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    Al-Mayadin hospital uses the standard ward design approved for the Hama extension

Shared risks

Risks that hit more than one project, managed at programme level.

25

Late land allocation and handover stalls closing the temporary wards

PRK-05-1·Escalate·Eng. Sara Al-Barazi

Affects

Open risks in the programme’s projects

4 risks

Open risks in the programme’s projects
  • Critical2
  • High2
  • Medium0
  • Low0
  • Risks 4
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High2 · Critical0 · Critical
40 · Low0 · Medium0 · Medium1 · High0 · Critical
30 · Low0 · Low0 · Medium0 · Medium1 · High
20 · Low0 · Low0 · Low0 · Medium0 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely4

Monitor0

Keep informed0

Salma Al-ZaimManage closelyEng. Fadi Al-DroubiManage closelyEng. Wael Al-KhawlaniManage closelyRasha Al-MudarresManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

National Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital Transformation
Chair: Dr. Samer Al-DaqqarNext meeting 2026-11-03
Authority Executive Council

Weekly · Quorum ⁦4⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital TransformationSalma Al-Zaim · Deputy President, Finance, Administration & the Investment Plan
Chair: Dr. Samer Al-DaqqarNext meeting 2026-10-28
Change Committee

Weekly · Quorum ⁦4⁩

Dr. Reem Al-Qabbani · Director, National Project Management OfficeOmar Al-Nahhas · Senior Finance & Contracts SpecialistRasha Al-Mudarres · Director General, Finance & Contracts
Chair: Dr. Ziad Al-AtassiNext meeting 2026-10-29

Programme projects

The programme’s performance is computed from these projects.

⁦2⁩ results
Export CSV
Manager
Hama National Hospital Upgrade & ExtensionPRJ-2026-007Eng. Sara Al-Barazi4ExecutionCritical⁦57%⁩SYP16BSYP19.5B⁦+22.0%⁩0.70Schedule performance index · 0.700.82Cost performance index · 0.82
Al-Mayadin General HospitalPRJ-2026-033Eng. Sara Al-Barazi3PlanningOn hold⁦2%⁩SYP5.3BSYP5.3B⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Total · 2SYP21.3BSYP24.8B
⁦1⁩–⁦2⁩ of ⁦2⁩

Budget shares

Budget shares

SYP 21.3B

Budget

  • Hama National Hospital Upgrade & ExtensionSYP 16B⁦75%⁩
  • Al-Mayadin General HospitalSYP 5.3B⁦25%⁩
Budget shares
CategoryValueShare
Hama National Hospital Upgrade & ExtensionSYP 16B⁦75%⁩
Al-Mayadin General HospitalSYP 5.3B⁦25%⁩
TotalSYP 21.3B⁦100%⁩