Change Committee
Controls change to scope, cost, schedule and contracts: assesses each request’s impact and rules within three working days of a complete file, re-baselining on approval.
Authority
Up to 10% of BAC or SYP 500M; extensions up to 90 days
Authority up to SYP 500M
Escalates to
National Projects Steering CommitteeRules within 3 working days of a complete file (§130)
Quorum
Four of six members, including Finance
Voting
Simple majority; a Finance objection on impact above SYP 125M sends it to the national steering committee
Members
66 with a vote
Quorum / voters
4/6Seats needed for a valid session
Sessions in 2026
418 decisions recorded
Resolutions
20 late
Next session
2026-10-29 · 13:00 — Change Committee — meeting 42
Members & roles
Chaired by Dr. Ziad Al-Atassi
- Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairAttended 39 of 41Since 2025-07-20
- Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syVice-chairAttended 40 of 41Since 2025-07-13
- Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syMemberAttended 38 of 41Since 2025-07-20
- Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syMemberAttended 31 of 41Since 2025-07-20
- Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syMemberAttended 35 of 41Since 2025-10-12
- Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sySecretaryAttended 41 of 41Since 2025-07-20