The project with the most weight on this KPI is “Hama National Hospital Upgrade & Extension”, with 75% of the linked budget, and it is Critical. Speeding it up is the fastest way to close the gap before December.
This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.
Approved in plan version 1.1Higher Council resolution HCED-2026-032026-03-25
No change requests on this item since the plan was approved.
Corrective actions
What we are doing to bring the KPI back on track, who owns it, and by when.
Hand over the east-wing wards of Hama National Hospital in two batches instead of one
Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014·fadi.aldroubi@psa.gov.syDue 2026-12-10In 43 days2026-12-10Hama National Hospital Upgrade & Extension
In progress
Comments
The owner, the Performance Measurement Office and leadership discussing the readings.
Eng. Sara Al-BaraziSenior Project Manager — Hospitals & Health Facilities2026-10-24 14:10
Two wings at Hama National Hospital, 260 beds in all, are handed over in November — we expect to come close to target.