Development Strategic Framework 2026–2030 and the 2026–2028 Medium-Term Plan

Review & update

Periodic reviews with their findings and decisions, and change requests on the plan with their reasons, effect on targets and approval decision.

Next review
2026-12-15

Mid-term review of the 2026–2030 framework

Reviews in 2026
3

Quarterly, held by the steering committee

Open change requests
4

In study or awaiting a decision

Approved requests
4

Carried into plan versions

Periodic plan reviews

The National Projects Steering Committee, chaired by the President of the Authority, meets every quarter, then for an annual review and a mid-term review. Each review has its findings, decisions and the change requests it raised.

  1. Mid-term reviewScheduled

    Mid-term review of the 2026–2030 framework

    2026-12-15 · National Projects Steering Committee

    Assess the whole recovery & stability phase before moving to the rebuilding phase, and set the 2027–2028 priorities in the medium-term plan.

    • The recovery & stability phase against its targets
    • Objectives with no initiative and unlinked projects
    • The rebuilding phase’s priorities and estimated allocations
    • Change requests pending on version 1.2

  2. Quarterly reviewHeld — results recorded

    Strategic performance review — Q3 2026

    2026-10-21 · National Projects Steering Committee

    Plan attainment
    ⁦90%⁩
    Objectives on track
    3 / 12
    KPIs on track
    14 / 30

    The plan is at 90% of its 2026 targets. The digital government services and neighbourhood reconstruction objectives are off track; four amendments were requested for version 1.2.

    4 findings3 decisions4 change requests

  3. Quarterly reviewCompleted

    Strategic performance review — Q2 2026

    2026-07-22 · National Projects Steering Committee

    Plan attainment
    ⁦89%⁩
    Objectives on track
    2 / 12
    KPIs on track
    12 / 30

    Progress on power and water, the Darayya replacement housing late; the request to weigh the growth & investment objective more was sent back for study.

    2 findings2 decisions1 change request

  4. Quarterly reviewCompleted

    Strategic performance review — Q1 2026

    2026-04-28 · National Projects Steering Committee

    Plan attainment
    ⁦86%⁩
    Objectives on track
    3 / 12
    KPIs on track
    14 / 30

    The first review on version 1.1; quarterly scorecards adopted for the Authority’s sectors and the partner ministries.

    1 finding1 decision

  5. Annual reviewCompleted

    Annual review 2025 and closing the transitional cycle

    2026-02-24 · National Projects Steering Committee

    Plan attainment
    ⁦78%⁩
    Objectives on track
    4 / 12
    KPIs on track
    15 / 30

    The year 2025 closed at 78%. Four change requests on the new framework were approved and issued as version 1.1.

    3 findings1 decision4 change requests

Change requests on the plan

Every proposed change to themes, directions, objectives, KPIs, initiatives and the identity: its reason, effect on targets, before-and-after value, approval path and decision. Select a request for its detail and to decide.

⁦9⁩ results
Export CSV
Current step
SCR-2026-09

Measure the national PMO maturity index half-yearly instead of yearly

KPI

Dr. Reem Al-QabbaniDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.sy2026-10-24Version ⁦1.2⁩In studyPreparation & study — National Strategy Directorate
SCR-2026-08

Raise the growth & investment objective’s weight in its theme from 60% to 70%

Objective

Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy2026-08-02Version ⁦1.2⁩Returned—
SCR-2026-07

Add “Innovation” to the Authority’s values

Value

Dr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.sy2026-10-08Version ⁦1.2⁩Awaiting decisionApproval — Higher Council for Economic Development
SCR-2026-06

Add the “Population & housing census” initiative

Initiative

Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy2026-10-22Version ⁦1.2⁩In studyPreparation & study — National Strategy Directorate
SCR-2026-05

Lower the 2026 target for citizen satisfaction with digital government services from 85% to 80%

KPI

Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004lina.alattar@psa.gov.sy2026-10-23Version ⁦1.2⁩Awaiting decisionApproval — The President of the Authority
SCR-2026-04

Move the power & water systems initiative under the core-infrastructure objective

Initiative

Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy2026-02-26Version ⁦1.1⁩Approved—
SCR-2026-03

Lower the 2026 target of the investment-savings KPI

KPI

Rasha Al-MudarresRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.sy2026-02-26Version ⁦1.1⁩Approved—
SCR-2026-02

Add two qualitative KPIs: data-governance maturity and governorate-plan quality

KPI

Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.sy2026-02-26Version ⁦1.1⁩Approved—
SCR-2026-01

Move five points of weight from “Governance & Digital Transformation” to “Reconstruction & Infrastructure”

Theme

Rana Al-SammanRana Al-SammanHead of National StrategyP-039rana.alsamman@psa.gov.sy2026-02-26Version ⁦1.1⁩Approved—