PRJ-2026-007Critical4ExecutionConstructionStalledDelivered by:Ministry of Health

Hama National Hospital Upgrade & Extension

Remove from watchlist

Extending Hama National Hospital with a new wing of 42 wards and theatres and upgrading its medical equipment, running 9 temporary wards so care never stops during the works.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SYP 16B

Actual cost

SYP 11.1B

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 19.5B

+SYP 3.5B

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−24

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦97%⁩ chance of a further slip within ⁦30⁩ days

From the SPI trend (⁦0.70⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦57% done against 82% planned⁩.

⁦SPI 0⁩.⁦70⁩, ⁦CPI 0⁩.⁦82⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Human DevelopmentSO-3.1Better access to health and education

Main initiative

SI-3.1.1Public hospitals rehabilitation

Contribution to the initiative⁦100%⁩

The project’s share of the initiative’s project budget (1 project)

Secondary links

Annual work-plan line
WP-2024-007
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦57%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦33%⁩

7 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Finishes⁦13%⁩
  • Detailed design⁦6%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Supply⁦10%⁩

Corrective planCP-2026-03

Awaiting approvalOverdue: ⁦1⁩

Unapproved finishing samples, a skilled-labour shortage at the MEP subcontractor, and the pricing dispute over variation 7

Actions

⁦0⁩ of ⁦4⁩ done

Next: Rule on the finishing samples or approve an equivalent · Eng. Sara Al-Barazi · 2026-10-15

Days won back

⁦0⁩ of ⁦60⁩

With the plan: 2027-06-01

Open the plan

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦97%⁩ of budget

SYP11.1B/ SYP16BSYP3.5Bprojected overrun(⁦22.0%⁩)
Actual spend
SYP11.1B
Committed
SYP15.5B
Approved budget
SYP16B
Estimate at completion
SYP19.5B

Next milestones

  • Provisional acceptance⁦2027-01-29⁩was ⁦2026-10-07⁩Late
  • Closure⁦2027-06-01⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦3⁩ approvals and ⁦3⁩ open actions on this project

Approvals & requests

From «My actions» for this project

Actions

⁦3⁩ open

  • Prepare the claims file for the dispute boardEng. Sara Al-BaraziIn 9 days2026-11-06High
  • Approve or reject the finishing samples with reasonsEng. Wael Al-Khawlani13 days overdue2026-10-15Critical
  • ⁦Commission an independent engineer to assess the 150⁩-day extensionEng. Fadi Al-DroubiIn 7 days2026-11-04High

Risks & impediments

3 open risks, exposure SYP 1.6B

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩1Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩RSK-0026Contractor’s financial claims piling up over unapproved change ordersProbability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0027Late delivery of operating-theatre equipment from the overseas supplierProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩1Probability: Possible · Impact: SevereHigh · Score ⁦15⁩RSK-0028Possible termination of the MEP subcontractor
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical1
  • High2
  • Medium0
  • Low0

Deliverables

⁦7⁩ of ⁦12⁩ approved

  • Project plan & baseline007-D1 · V1 · CRT-007-01⁦3%⁩Eng. Sara Al-Barazi2024-06-182024-06-18Approved
  • Monitoring & reporting007-D2 · V1 · CRT-007-02⁦3%⁩Eng. Fadi Al-Droubi2024-09-102024-09-10Approved
  • Detailed design007-D3 · V1 · CRT-007-03⁦6%⁩Eng. Fadi Al-Droubi2024-12-032024-12-03Approved
  • Permits & approvals007-D4 · V1 · CRT-007-04⁦6%⁩Eng. Abdulrahman Al-Kilani2025-02-252025-02-25Approved
  • Site works & excavation007-D5 · V1 · CRT-007-05⁦13%⁩Eng. Abdulrahman Al-Kilani2025-05-212025-05-21Approved
  • Structure007-D6 · V1 · CRT-007-06⁦13%⁩Eng. Sara Al-Barazi2025-08-132025-08-13Approved
  • Finishes007-D7 · V1 · CRT-007-07⁦13%⁩Eng. Fadi Al-Droubi2025-11-052025-11-05Approved
  • Supply007-D8 · V1⁦10%⁩Eng. Sara Al-Barazi273 days overdue2026-01-28Submitted
  • Installation007-D9 · V0⁦10%⁩Eng. Fadi Al-Droubi189 days overdue2026-04-22Draft
  • Testing & commissioning007-D10 · V0⁦9%⁩Eng. Abdulrahman Al-Kilani104 days overdue2026-07-16Draft
  • Provisional acceptance007-D11 · V0⁦7%⁩Eng. Fadi Al-Droubi20 days overdue2026-10-08Draft
  • Final acceptance007-D12 · V0⁦7%⁩Eng. Abdulrahman Al-KilaniIn 64 days2026-12-31Draft

Team, contracts & documents

Team

4 members

Eng. Sara Al-Barazi · Senior Project Manager — Hospitals & Health FacilitiesEng. Fadi Al-Droubi · Director General, Human Development ProjectsOmar Al-Nahhas · Senior Finance & Contracts SpecialistEng. Adnan Al-Mohammad · Senior Site Engineer (Contractor)
  • Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesProject managerP-022sara.albarazi@psa.gov.sy⁦90%⁩
  • Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsProject ownerP-014fadi.aldroubi@psa.gov.sy⁦25%⁩
  • Omar Al-NahhasOmar Al-NahhasSenior Finance & Contracts SpecialistHama hospital extension contract & certificatesP-007omar.alnahhas@psa.gov.sy⁦20%⁩
  • Eng. Adnan Al-MohammadEng. Adnan Al-MohammadSenior Site Engineer (Contractor)Site engineer (MEP)P-043adnan.almohammad@psa.gov.sy⁦40%⁩