CR-2026-005Hama National Hospital Upgrade & Extension

Change order 7: medical gases and HVAC redesign

ContractEscalatedImpact level: Major55 days overdue2026-09-03

Justification and the cost, schedule and risk impact, with a recommendation.

Electronic form

Impact analysis

Before and after — as it will show in the baseline if approved

Cost

+SYP 465M

Current budgetSYP 16B

After the changeSYP 16.5B

+2.9%

Schedule

+⁦40⁩ d
  • Baseline finish2026-12-31
  • New finish2027-02-09

Benefits

+4%

14% less energy a year and theatres up to standard

⁦+4⁩% of expected benefits

Reason for change

Medical gases and HVAC insufficient after extra operating theatres and the intensive-care wing were added

Justification

Without it the new wards fail the Ministry of Health facility standards

PMO recommendation

Defer

The pricing dispute was referred to the national projects steering committee

Approval workflow

  1. Submitted

    Eng. Sara Al-Barazi

    Done2026-08-20

  2. PM review

    Eng. Sara Al-Barazi

    Done2026-08-21

  3. Impact analysis

    Kinan Azzam

    Done2026-08-25

  4. Finance & procurement

    Rasha Al-Mudarres

    Done2026-08-26

  5. 5

    Change committee recommendation

    Dr. Ziad Al-Atassi

    Escalated2026-10-13

  6. 6

    Executive Council decision

    Dr. Samer Al-Daqqar

    Now

  7. 7

    Baseline updated

    Eng. Sara Al-Barazi

    Later

Why this route

The route is built from the request’s kind and impact level under the approved authority matrix.

Impact levelMajorAbove SYP 125M or 90 days

  • A cost impact of SYP 465M is above SYP 125M — «major»: the Change Committee recommends and the Executive Council decides.
  • It touches a signed contract, so Finance & Procurement review it contractually.

Awaiting the Executive Council’s decision

Change committee vote

Members vote before or during the meeting; the decision is taken once quorum is met

National Steering Committee — October13 October 2026 10:00Main meeting hall — Authority HQ, Kafr Sousa
  • Dr. Ziad Al-AtassiDeputy President, Strategy & PerformanceDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syChairApprove with conditions
  • Dr. Reem Al-QabbaniDirector, National Project Management OfficeDr. Reem Al-QabbaniDirector, National Project Management OfficeP-002reem.alqabbani@psa.gov.syYouApprove
  • Omar Al-NahhasSenior Finance & Contracts SpecialistOmar Al-NahhasSenior Finance & Contracts SpecialistP-007omar.alnahhas@psa.gov.syReject
  • Rasha Al-MudarresDirector General, Finance & ContractsRasha Al-MudarresDirector General, Finance & ContractsP-018rasha.almudarres@psa.gov.syReject
  • Eng. Rita GhanemEnterprise ArchitectEng. Rita GhanemEnterprise ArchitectP-031rita.ghanem@psa.gov.syApprove
  • Eng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.syApprove with conditions
6/6Quorum met
  • Approve2
  • Approve with conditions2
  • Reject2
  • Abstain0

Awaiting the impact analysis