Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

RSK-0026Hama National Hospital Upgrade & Extension

Contractor’s financial claims piling up over unapproved change orders

20CriticalEscalatedMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Variations carried out before formal approval, and disputes over their pricing

Preventive controls

  • Refer the claims to the dispute committee named in the contract
  • List every unapproved variation with the independent engineer

1 / 2

Event

Contractor’s financial claims piling up over unapproved change orders

20CriticalTrigger

A dispute-committee recommendation above SYP 625M

Contingency

An amicable settlement within a ceiling set by the national projects steering committee

Impact

Claims that could reach SYP 1.025bn and a strained contract relationship

SYP 1B

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
20Critical

Residual

5
4
3
2
1
1
2
3
4
5
12Medium

Exposure

SYP 1B

Residual

⁦40⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 3 days ago

  1. Project manager

    Eng. Sara Al-Barazi

    Currently followed up here
  2. Programme manager

    Current level

    Eng. Sara Al-Barazi

    Automatically at 15 days unreviewed · in 12 days
  3. 3

    PMO director

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · in 17 days
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦1⁩ of ⁦2⁩ done
  • Refer the claims to the dispute committee named in the contract

    Eng. Sara Al-BaraziEng. Sara Al-BaraziSenior Project Manager — Hospitals & Health FacilitiesP-022sara.albarazi@psa.gov.sy
    Done2026-10-132026-10-13
  • List every unapproved variation with the independent engineer

    Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy
    In progressIn 13 days2026-11-10

Trigger

A dispute-committee recommendation above SYP 625M

Contingency

An amicable settlement within a ceiling set by the national projects steering committee

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close