Contractor claims file — Hama National Hospital extension

RestrictedIn reviewV2Checked out to Eng. Sara Al-BaraziLegal hold

The Hama National Hospital extension contractor’s claims for variations and extension of time, with technical and legal responses.

More
Showing version:

Restricted

Syrian Arab Republic

Planning and Statistics Authority

National Project Management Office (PMO)

Code
DOC-0213
Version
V2
Date
2026-10-24

Contractor claims file — Hama National Hospital extension

Hama National Hospital Upgrade & Extension

The parties

This contract is made between the public body that owns the project (first party) and the contractor named in the data sheet (second party), under the public contracts law (⁦Law 51 of 2004⁩) and the general tender conditions.

Project
Hama National Hospital Upgrade & Extension (⁦PRJ-2026-007⁩)
Project manager
Eng. Sara Al-Barazi
Budget
⁦SYP 16⁩.⁦00bn⁩
Progress
⁦57% actual against 82% planned⁩
Forecast finish
⁦2027-06-01⁩

Key terms

  • ⁦Delay penalty 0⁩.⁦5% a week⁩, ⁦capped at 10% of the contract value⁩
  • A ⁦10% performance bond valid until final acceptance⁩
  • ⁦10% retention on every certificate⁩

⁦Addendum 1⁩

⁦This addendum amends the payment schedule and adds complementary works within 10% of the contract value⁩.

Prepared by

Eng. Sara Al-Barazi
Issued from Munjaz — valid only once approved electronically1 / 1