Hamza Al-HusseinLeave on critical workHamza’s leave falls in the last two weeks of the “National interoperability framework integration” package, on the critical pathRecommendation
Eng. Maher Al-HamawiLeave on critical workMaher is away during the commissioning tests of the eastern substation in Aleppo, with no named deputy
Reallocation recommendations
Copilot proposes them from skills, loads and the critical path — apply one to see the effect at once
Reassigning Eng. Saleh Al-Bakir cuts the unified e-services platform’s delay by 12 days
Raise Saleh’s allocation on the unified e-services platform from 15% to 50% for 10 weeks and move the ministry back-office integration to him from Hamza Al-Hussein — Hamza returns to 100% and the “National interoperability framework integration” on the critical path speeds up.
Moaz Kaddour starts the plan tracker’s data preparation
Moaz is at 70% with data engineering (4/5). Giving 25% of him to the plan tracker from December covers half an open seat and pulls the historic-indicator data preparation forward by nine days.
Deferring the unified contact centre a month eases the January peak
Eng. George Haddad runs three live projects and reaches 107% in January if the proposed contact centre starts alongside them. Moving its start to February brings him to 84% that month with no effect on his running projects.