PRJ-2026-020Off track4ExecutionConstructionStalledDelivered by:Ministry of Local Administration and Environment

Douma Wastewater Treatment Plant

Remove from watchlist

A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 8.6B

Actual cost

SYP 4B

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 9.1B

+SYP 453.9M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−21

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦81%⁩ chance of a further slip within ⁦60⁩ days

From the SPI trend (⁦0.80⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦44% done against 55% planned⁩.

⁦SPI 0⁩.⁦80⁩, ⁦CPI 0⁩.⁦95⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.1Rehabilitate core energy, water and transport infrastructure

Main initiative

SI-2.2.1Replacement housing & rebuilding damaged areas

Contribution to the initiative⁦17%⁩

The project’s share of the initiative’s project budget (3 projects)

Annual work-plan line
WP-2024-020
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦44%⁩

Awaiting acceptance ⁦12%⁩

Not handed in ⁦44%⁩

6 deliverables accepted

  • Site works & excavation⁦13%⁩
  • Structure⁦13%⁩
  • Detailed design⁦6%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Finishes⁦12%⁩

Corrective planCP-2026-04

Approved — under way

Clay layers, voids and groundwater under the foundations of axes 12 to 16 that the initial soil tests missed

Actions

⁦1⁩ of ⁦5⁩ done

Next: Redesign the foundations through a change request · Eng. Qasem Al-Hariri · 2026-11-04

Days won back

⁦0⁩ of ⁦33⁩

With the plan: 2027-08-03

Open the plan

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦92%⁩ of budget

SYP4B/ SYP8.6BSYP453.9Mprojected overrun(⁦5.3%⁩)
Actual spend
SYP4B
Committed
SYP7.9B
Approved budget
SYP8.6B
Estimate at completion
SYP9.1B

Next milestones

  • Provisional acceptance⁦2027-04-22⁩was ⁦2027-03-05⁩Late
  • Closure⁦2027-08-03⁩was ⁦2027-05-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • ⁦Approve the geotechnical report for axes 12⁩–⁦16 at the Douma plant⁩Eng. Qasem Al-HaririIn 11 days2026-11-08High

Risks & impediments

2 open risks, exposure SYP 885M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩1Probability: Likely · Impact: SevereCritical · Score ⁦20⁩RSK-0034Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩1Probability: Possible · Impact: MajorMedium · Score ⁦12⁩RSK-0035Pile lengths exceeding contract quantitiesProbability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical1
  • High0
  • Medium1
  • Low0

Deliverables

⁦6⁩ of ⁦12⁩ approved

  • Project plan & baseline020-D1 · V1 · CRT-020-01⁦3%⁩Eng. Qasem Al-Hariri2024-10-192024-10-19Approved
  • Monitoring & reporting020-D2 · V1 · CRT-020-02⁦3%⁩Jwan Othman2025-01-142025-01-14Approved
  • Detailed design020-D3 · V1 · CRT-020-03⁦6%⁩Jwan Othman2025-04-102025-04-10Approved
  • Permits & approvals020-D4 · V1 · CRT-020-04⁦6%⁩Salma Al-Zaim2025-07-062025-07-06Approved
  • Site works & excavation020-D5 · V1 · CRT-020-05⁦13%⁩Salma Al-Zaim2025-10-012025-10-01Approved
  • Structure020-D6 · V1 · CRT-020-06⁦13%⁩Eng. Qasem Al-Hariri2025-12-272025-12-27Approved
  • Finishes020-D7 · V1⁦12%⁩Jwan Othman219 days overdue2026-03-23Submitted
  • Supply020-D8 · V0⁦10%⁩Eng. Qasem Al-Hariri132 days overdue2026-06-18Draft
  • Installation020-D9 · V0⁦10%⁩Jwan Othman45 days overdue2026-09-13Draft
  • Testing & commissioning020-D10 · V0⁦10%⁩Salma Al-ZaimIn 42 days2026-12-09Draft
  • Provisional acceptance020-D11 · V0⁦7%⁩Jwan OthmanIn 128 days2027-03-05Draft
  • Final acceptance020-D12 · V0⁦7%⁩Salma Al-ZaimIn 215 days2027-05-31Draft

Team, contracts & documents

Team

2 members

Eng. Qasem Al-Hariri · Director, Transport & Housing Projects
  • Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsProject managerP-020qasem.alhariri@psa.gov.sy⁦50%⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close