Douma Wastewater Treatment Plant
Remove from watchlistA wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
+SYP 453.9M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started
Scope statementRequired at this stage
What the project delivers, what it does not, and when a deliverable counts as accepted.
A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
In scope
- A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
- Syrian Arab Building Code compliance
- An approved plan to keep services running for residents during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the project owner
- Main deliverable — final stageMeets the approved specification, signed off by the project owner
Scope baselineRequired at this stage
Every approved change creates a new baseline
- 1
SB-1Current2024-07-25
Baseline approved at the planning gate
BudgetSYP8.6BFinish2027-05-31
Requirements registerRequired at this stage
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
33%
2/6 · test result is a pass
Accepted
33%
2/6 · signed off by the business owner
Display options
| REQ-020-01 | Reach the target capacity of rehabilitated facilities | Business | Must | In progress | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | SB-1 | |
| REQ-020-02 | Meet the approved technical specs | Technical | Must | Approved | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | SB-1 | |
| REQ-020-03 | Services to residents continue during the works | Functional | Must | In progress | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | SB-1 | |
| REQ-020-04 | Syrian Arab Building Code | Regulatory | Should | In progress | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | SB-1 | |
| REQ-020-05 | Civil-defence requirements | Regulatory | Should | In progress | Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy | SB-1 | |
| REQ-020-06 | Site and systems security | Security | Could | Approved | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy | SB-1 |
Traceability matrixRequired at this stage
Requirement → deliverable → task → test → acceptance. No requirement has a gap.