Planning
Project management plan
Schedule, deliverables, risks, communications, quality and benefits
- Form no.
- PSA-PMO-F05
- Template edition
- 2.0
- Version
- V2
- Form date
- 2024-06-27
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-020
- Project
- Douma Wastewater Treatment Plant
- Portfolio
- Reconstruction & Infrastructure Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Salma Al-Zaim
- Project manager
- Eng. Qasem Al-Hariri
1ScheduleAuto-filled
From the project schedule and its approved baseline.
Start
2024-06-02
Baseline finish
2027-05-31
Forecast finish
2027-08-03
SPI
0.80
| Milestone | Planned | Forecast | Slip |
|---|---|---|---|
| Project plan approved | 2025-01-14 | 2025-05-14 | +120 days |
| Designs approved | 2025-07-06 | 2026-02-03 | +212 days |
| Build complete | 2026-03-23 | 2027-03-09 | +351 days |
| Testing & acceptance complete | 2026-12-09 | 2027-06-04 | +177 days |
| Final handover | 2027-05-31 | 2027-08-01 | +62 days |
2DeliverablesAuto-filled
| Deliverable | Weight | Due | Owner |
|---|---|---|---|
| Project plan & baseline | 3% | 2024-10-19 | Eng. Qasem Al-Hariri |
| Monitoring & reporting | 3% | 2025-01-14 | Jwan Othman |
| Detailed design | 6% | 2025-04-10 | Jwan Othman |
| Permits & approvals | 6% | 2025-07-06 | Salma Al-Zaim |
| Site works & excavation | 13% | 2025-10-01 | Salma Al-Zaim |
| Structure | 13% | 2025-12-27 | Eng. Qasem Al-Hariri |
| Finishes | 12% | 2026-03-23 | Jwan Othman |
| Supply | 10% | 2026-06-18 | Eng. Qasem Al-Hariri |
| Installation | 10% | 2026-09-13 | Jwan Othman |
| Testing & commissioning | 10% | 2026-12-09 | Salma Al-Zaim |
| Provisional acceptance | 7% | 2027-03-05 | Jwan Othman |
| Final acceptance | 7% | 2027-05-31 | Salma Al-Zaim |
| Accepted with a certificate | 44% | — | — |
3RisksAuto-filled
4CommunicationsAuto-filled
| Audience | Need | Frequency | Owner |
|---|---|---|---|
| Project sponsor | Status and decisions needed | Monthly | Eng. Qasem Al-Hariri |
| Project owner | Deliverable status and acceptance dates | Fortnightly | Eng. Qasem Al-Hariri |
| PMO | Data and indicator updates | Weekly | Eng. Qasem Al-Hariri |
| Beneficiaries | What changes and when | At each milestone | Eng. Qasem Al-Hariri |
| Team member | Role | Allocation |
|---|---|---|
| Eng. Qasem Al-Hariri | Project manager | 50% |
| — | Planning & scheduling engineer | 50% |
5QualityAuto-filled
- Quality leadAuto-filled
- Eng. Adnan Al-Mohammad
- Review cadenceAuto-filled
- Inspection of each foundation axis after striking; a design review at every change
- Next reviewAuto-filled
- 2026-11-02
| Quality criterion | Threshold | Now | Met |
|---|---|---|---|
| Crack width in the basement walls | Under 0.2 mm | 0.3 mm at axis 7 | No |
| Rebar cover | 75 mm for foundations | Compliant in 14 of 14 | Yes |
6BenefitsAuto-filled
| Benefit | Baseline | Target | Owner |
|---|---|---|---|
| No benefits recorded | |||
Approval logChain: Project management plan approval · version 1
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Qasem Al-HaririDirector, Transport & Housing Projects | Submitted | — | 2024-06-27 12:03 |
| 2 | Methodology review — PMO | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | Complete against the project management plan template. | 2024-07-02 14:05 |
| 3 | Technical acceptance — project owner | Technical acceptance | Jwan OthmanProject owner | Approved | — | 2024-07-03 09:12 |
| 4 | Cash flow & financial commitment | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2024-07-04 13:58 |
| 5 | Plan aligned with the contracts | Financial approval | Abdullah Al-UjailiProcurement & contracts | Approved | — | 2024-07-08 14:35 |
| 6 | Sponsor approval | Technical acceptance | Salma Al-ZaimProject sponsor | Approved | — | 2024-07-09 12:33 |
Signatures
Methodology review — PMO
Mariam Al-Zoubi
Approved2024-07-02
Technical acceptance — project owner
Jwan Othman
Approved2024-07-03
Cash flow & financial commitment
Rasha Al-Mudarres
Approved2024-07-04
Plan aligned with the contracts
Abdullah Al-Ujaili
Approved2024-07-08
Sponsor approval
Salma Al-Zaim
Approved2024-07-09