PRJ-2026-020Off track4ExecutionConstructionStalledDelivered by:Ministry of Local Administration and Environment

Douma Wastewater Treatment Plant

Remove from watchlist

A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 8.6B

Actual cost

SYP 4B

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 9.1B

+SYP 453.9M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
PSA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2024-06-27⁩
ApprovedPRJ-2026-020Douma Wastewater Treatment Plant

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-020
Project
Douma Wastewater Treatment Plant
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Development Projects Follow-up Sector
Sponsor
Salma Al-Zaim
Project manager
Eng. Qasem Al-Hariri

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2024-06-02⁩

Baseline finish

⁦2027-05-31⁩

Forecast finish

⁦2027-08-03⁩

SPI

0.80

MilestonePlannedForecastSlip
Project plan approved⁦2025-01-14⁩⁦2025-05-14⁩+120 days
Designs approved⁦2025-07-06⁩⁦2026-02-03⁩+212 days
Build complete⁦2026-03-23⁩⁦2027-03-09⁩+351 days
Testing & acceptance complete⁦2026-12-09⁩⁦2027-06-04⁩+177 days
Final handover⁦2027-05-31⁩⁦2027-08-01⁩+62 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦3%⁩⁦2024-10-19⁩Eng. Qasem Al-Hariri
Monitoring & reporting⁦3%⁩⁦2025-01-14⁩Jwan Othman
Detailed design⁦6%⁩⁦2025-04-10⁩Jwan Othman
Permits & approvals⁦6%⁩⁦2025-07-06⁩Salma Al-Zaim
Site works & excavation⁦13%⁩⁦2025-10-01⁩Salma Al-Zaim
Structure⁦13%⁩⁦2025-12-27⁩Eng. Qasem Al-Hariri
Finishes⁦12%⁩⁦2026-03-23⁩Jwan Othman
Supply⁦10%⁩⁦2026-06-18⁩Eng. Qasem Al-Hariri
Installation⁦10%⁩⁦2026-09-13⁩Jwan Othman
Testing & commissioning⁦10%⁩⁦2026-12-09⁩Salma Al-Zaim
Provisional acceptance⁦7%⁩⁦2027-03-05⁩Jwan Othman
Final acceptance⁦7%⁩⁦2027-05-31⁩Salma Al-Zaim
Accepted with a certificate⁦44%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
RSK-0034Unforeseen ground conditions and groundwater at the foundations of axes 12 to 1620EscalateEng. Qasem Al-Hariri
RSK-0035Pile lengths exceeding contract quantities12MitigateEng. Qasem Al-Hariri

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyEng. Qasem Al-Hariri
Project ownerDeliverable status and acceptance datesFortnightlyEng. Qasem Al-Hariri
PMOData and indicator updatesWeeklyEng. Qasem Al-Hariri
BeneficiariesWhat changes and whenAt each milestoneEng. Qasem Al-Hariri
Team memberRoleAllocation
Eng. Qasem Al-HaririProject manager⁦50%⁩
—Planning & scheduling engineer⁦50%⁩

5QualityAuto-filled

Quality leadAuto-filled
Eng. Adnan Al-Mohammad
Review cadenceAuto-filled
Inspection of each foundation axis after striking; a design review at every change
Next reviewAuto-filled
⁦2026-11-02⁩
Quality criterionThresholdNowMet
Crack width in the basement wallsUnder 0.2 mm0.3 mm at axis 7No
Rebar cover75 mm for foundationsCompliant in 14 of 14Yes

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Qasem Al-HaririDirector, Transport & Housing ProjectsSubmitted—⁦2024-06-27⁩ 12:03
2Methodology review — PMOMethodology reviewMariam Al-ZoubiPMO — analystApprovedComplete against the project management plan template.⁦2024-07-02⁩ 14:05
3Technical acceptance — project ownerTechnical acceptanceJwan OthmanProject ownerApproved—⁦2024-07-03⁩ 09:12
4Cash flow & financial commitmentFinancial approvalRasha Al-MudarresFinanceApproved—⁦2024-07-04⁩ 13:58
5Plan aligned with the contractsFinancial approvalAbdullah Al-UjailiProcurement & contractsApproved—⁦2024-07-08⁩ 14:35
6Sponsor approvalTechnical acceptanceSalma Al-ZaimProject sponsorApproved—⁦2024-07-09⁩ 12:33

Signatures

Methodology review — PMO

Mariam Al-Zoubi

Approved⁦2024-07-02⁩

Technical acceptance — project owner

Jwan Othman

Approved⁦2024-07-03⁩

Cash flow & financial commitment

Rasha Al-Mudarres

Approved⁦2024-07-04⁩

Plan aligned with the contracts

Abdullah Al-Ujaili

Approved⁦2024-07-08⁩

Sponsor approval

Salma Al-Zaim

Approved⁦2024-07-09⁩

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Eng. Qasem Al-Hariri on ⁦2024-06-27⁩

  1. Methodology review

    Methodology review — PMO

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2024-07-02⁩ at ⁦14:05⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Jwan Othman · Project owner

    Approved · ⁦2024-07-03⁩ at ⁦09:12⁩

  3. Financial approval

    Cash flow & financial commitment

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Approved · ⁦2024-07-04⁩ at ⁦13:58⁩

  4. Financial approval

    Plan aligned with the contracts

    Abdullah Al-Ujaili · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-07-08⁩ at ⁦14:35⁩

  5. Technical acceptance

    Sponsor approval

    Salma Al-Zaim · Project sponsor

    Approved · ⁦2024-07-09⁩ at ⁦12:33⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-06-27⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Eng. Qasem Al-Hariri

  2. V1Returned for edit⁦2024-06-13⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Eng. Qasem Al-Hariri