PRJ-2026-020Off track4ExecutionConstructionStalledDelivered by:Ministry of Local Administration and Environment
Douma Wastewater Treatment Plant
Remove from watchlistA wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
Project managerEng. Qasem Al-HaririProject sponsorSalma Al-ZaimProgrammeDamaged Areas Reconstruction Programme
Early warning: 81% chance of slipping within 60 days
Budget (BAC)
SYP 8.6B
Actual cost
SYP 4B
46% of budget
Progress
44%Awaiting acceptance 12%
Estimate at completion
SYP 9.1B
+SYP 453.9M
SPI · CPI
0.80Schedule performance index · 0.800.95Cost performance index · 0.95
Forecast finish
2027-08-03
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started