PRJ-2026-020Off track4ExecutionConstructionStalledDelivered by:Ministry of Local Administration and Environment

Douma Wastewater Treatment Plant

Remove from watchlist

A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 8.6B

Actual cost

SYP 4B

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 9.1B

+SYP 453.9M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Douma Wastewater Treatment Plant

APPROVEDV2Approved ⁦2024-05-31⁩

1Project identity

Required at this stage
Project name
Douma Wastewater Treatment Plant
Project code
PRJ-2026-020
Project sponsor
Salma Al-ZaimSalma Al-ZaimDeputy President, Finance, Administration & the Investment PlanP-012salma.alzaim@psa.gov.sy
Project manager
Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy
Project owner
Jwan OthmanJwan OthmanDirector, Partnerships & Development FinanceP-051jwan.othman@psa.gov.sy
Portfolio & programme
Reconstruction & Infrastructure PortfolioDamaged Areas Reconstruction Programme
Type & methodology
Infrastructure · Construction
Current phase
4Execution

2Background & rationale

Required at this stage

A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.

3Objectives

Required at this stage
  1. 1Rehabilitate core energy, water and transport infrastructure
  2. 2Rebuild damaged areas and provide replacement housing

4Scope

Required at this stage

In scope

  • A wastewater treatment plant in Douma serving the city and nearby towns, financed by the Syrian Development Fund, with the main trunk lines and treated water reused for irrigation.
  • Syrian Arab Building Code compliance
  • An approved plan to keep services running for residents during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Syrian Arab Building Code compliance
  2. 2An approved plan to keep services running for residents during the works
  3. 3Civil-defence requirements

6Deliverables

Required at this stage
1Project management plan⁦2024-07-16⁩
2Main deliverable — stage 1⁦2025-12-12⁩
3Main deliverable — final stage⁦2026-12-29⁩
4Final report⁦2027-05-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2024-05-31⁩
  2. Contract signed⁦2024-11-24⁩
  3. 50% of works complete⁦2025-12-12⁩
  4. Provisional acceptance⁦2027-03-05⁩
  5. Closure⁦2027-05-31⁩

8Budget

Required at this stage
  • Main contract⁦72.0%⁩SYP6.2B
  • Supervision & consulting⁦14.0%⁩SYP1.2B
  • Internal team⁦9.0%⁩SYP777.5M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩SYP432.5M
The delivering body’s investment-plan allocationsTotalSYP8.6B

9Timeline

Required at this stage
Start
2024-06-022 June 2024
Baseline finish
2027-05-3131 May 2027
Duration
⁦36⁩ months

10Key risks

Required at this stage
  • High⁦Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16⁩
  • MediumPile lengths exceeding contract quantities

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority