Late groundwater treatment at the Douma plant and late land allocation for the replacement housing
PRK-07-1·Escalate·Eng. Qasem Al-Hariri
Programme · PG-07 · Reconstruction & Infrastructure Portfolio
Darayya replacement housing, the Douma plant, the Deir ez-Zor suspension bridge and Maarat al-Numan’s infrastructure.
incl. SYP 1B programme reserve
34% of budget
Estimate at completion
Planned 37%
Cost performance index 0.95
Manager
Eng. Qasem Al-Hariri
Director, Transport & Housing Projects
Sponsor
Eng. Wassim Al-Azm
Director General, Infrastructure & Reconstruction Projects
Projects
4 projects
2024-03-03 — 2028-12-31
On track 1At risk 1Off track 2
What the programme must achieve, and the strategic objectives it serves.
Replacement housing in Darayya for returning families, with full utility networks
Core infrastructure — the Douma treatment plant and the Deir ez-Zor suspension bridge — that brings damaged areas back to life
Rehabilitating Maarat al-Numan’s infrastructure with Idlib Governorate
From baseline to target
Public facilities rehabilitated this year
by 2026Population served by rehabilitated water and sewer networks
by 2027Temporary-housing cost avoided (cumulative to 2035)
by 2028One lane per project: start to forecast finish, with the progress earned and the baseline finish.
What waits on what. Red links are on the programme’s critical path.
Critical path
Critical
The Darayya housing’s sewer networks need the Douma plant running before the blocks are occupied
Critical
The Maarat al-Numan works apply the design standards approved for the Darayya project
Risks that hit more than one project, managed at programme level.
Late groundwater treatment at the Douma plant and late land allocation for the replacement housing
PRK-07-1·Escalate·Eng. Qasem Al-Hariri
Steel and cement shortages at the peak of the reconstruction season
PRK-07-2·Mitigate·Eng. Qasem Al-Hariri
8 risks
Impact
| Probability \ Impact | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|
| 5 | 0 · Low | 0 · Medium | 0 · High | 1 · Critical | 0 · Critical |
| 4 | 0 · Low | 0 · Medium | 0 · Medium | 2 · High | 2 · Critical |
| 3 | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium | 1 · High |
| 2 | 0 · Low | 0 · Low | 0 · Low | 0 · Medium | 1 · Medium |
| 1 | 0 · Low | 0 · Low | 0 · Low | 0 · Low | 0 · Low |
Damaged neighbourhoods covered by reconstruction plans
41%
+3
Target 60%68%
Infrastructure projects delivered to plan
73%
+1
Target 85%86%
Population served by rehabilitated water networks
76.4%
+1
Target 78.0%98%
Transactions completed at citizen service centres per month
4.1thousand transactions
0
Target 4.591%
Power against interest; click a person to see their role.
Keep satisfied0
Manage closely5
Monitor0
Keep informed0
Interest
What the committees decided on the programme’s projects, and what the programme raised to them.
Committees
Monthly · Quorum 5
Members
6 members
Weekly · Quorum 4
As needed · Quorum 3
The programme’s performance is computed from these projects.
Display options
| Manager | ||||||||
|---|---|---|---|---|---|---|---|---|
| Darayya Replacement HousingPRJ-2026-002 | Eng. Qasem Al-Hariri | 4Execution | Off track | 42% | SYP29.5B | SYP31.7B+7.5% | 0.82Schedule performance index · 0.82 | 0.93Cost performance index · 0.93 |
| Douma Wastewater Treatment PlantPRJ-2026-020 | Eng. Qasem Al-Hariri | 4Execution | Off track | 44% | SYP8.6B | SYP9.1B+5.3% | 0.80Schedule performance index · 0.80 | 0.95Cost performance index · 0.95 |
| Deir ez-Zor Suspension Bridge ReconstructionPRJ-2026-021 | Eng. Wael Al-Khawlani | 3Planning | On track | 2% | SYP13B | SYP13B0.0% | 1.00Schedule performance index · 1.00 | 1.00Cost performance index · 1.00 |
| Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernoratePRJ-2026-034 | Eng. Wael Al-Khawlani | 4Execution | At risk | 33% | SYP6B | SYP6.2B+4.2% | 0.89Schedule performance index · 0.89 | 0.96Cost performance index · 0.96 |
| Total · 4 | SYP57.1B | SYP60B |
SYP 57.1B
Budget
| Category | Value | Share |
|---|---|---|
| Darayya Replacement Housing | SYP 29.5B | 52% |
| Douma Wastewater Treatment Plant | SYP 8.6B | 15% |
| Deir ez-Zor Suspension Bridge Reconstruction | SYP 13B | 23% |
| Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate | SYP 6B | 10% |
| Total | SYP 57.1B | 100% |