Programme · PG-07 · Reconstruction & Infrastructure Portfolio

Damaged Areas Reconstruction Programme

Off track

Darayya replacement housing, the Douma plant, the Deir ez-Zor suspension bridge and Maarat al-Numan’s infrastructure.

Approved budget
SYP 58.1B

incl. SYP 1B programme reserve

Actual spend
SYP 19.6B

⁦34%⁩ of budget

EAC
SYP 60B+5.1%

Estimate at completion

Progress
⁦31%⁩

Planned ⁦37%⁩

Schedule performance index
0.87

Cost performance index 0.95

Manager

Eng. Qasem Al-Hariri

Director, Transport & Housing Projects

Sponsor

Eng. Wassim Al-Azm

Director General, Infrastructure & Reconstruction Projects

Projects

4 projects

2024-03-03 — 2028-12-31

On track 1At risk 1Off track 2

Programme objectives

What the programme must achieve, and the strategic objectives it serves.

  1. 1

    Replacement housing in Darayya for returning families, with full utility networks

  2. 2

    Core infrastructure — the Douma treatment plant and the Deir ez-Zor suspension bridge — that brings damaged areas back to life

  3. 3

    Rehabilitating Maarat al-Numan’s infrastructure with Idlib Governorate

Programme benefits

From baseline to target

  • Public facilities rehabilitated this year

    by ⁦2026⁩
    Baseline 0Current 48 facilitiesTarget 60
  • Population served by rehabilitated water and sewer networks

    by ⁦2027⁩
    Baseline 71Current 76.4 %Target 78
  • Temporary-housing cost avoided (cumulative to 2035)

    by ⁦2028⁩
    Baseline 0Current 15.3 SYP bnTarget 22.5

Roadmap

One lane per project: start to forecast finish, with the progress earned and the baseline finish.

EarnedRemainingBaseline finishSlip
20242025202620272028
2027-09-12
2027-08-03
2027-09-28
2028-12-31

Dependencies between projects

What waits on what. Red links are on the programme’s critical path.

Critical path

What each project needs from the one before

  • Critical

    The Darayya housing’s sewer networks need the Douma plant running before the blocks are occupied

  • Critical

    The Maarat al-Numan works apply the design standards approved for the Darayya project

Shared risks

Risks that hit more than one project, managed at programme level.

20

Late groundwater treatment at the Douma plant and late land allocation for the replacement housing

PRK-07-1·Escalate·Eng. Qasem Al-Hariri

Affects
12

Steel and cement shortages at the peak of the reconstruction season

PRK-07-2·Mitigate·Eng. Qasem Al-Hariri

Affects

Open risks in the programme’s projects

8 risks

Open risks in the programme’s projects
  • Critical3
  • High3
  • Medium2
  • Low0
  • Risks 8
Probability
5
4
3
2
1
12345

Impact

Open risks in the programme’s projects
Probability \ Impact12345
50 · Low0 · Medium0 · High1 · Critical0 · Critical
40 · Low0 · Medium0 · Medium2 · High2 · Critical
30 · Low0 · Low0 · Medium1 · Medium1 · High
20 · Low0 · Low0 · Low0 · Medium1 · Medium
10 · Low0 · Low0 · Low0 · Low0 · Low

Programme KPIs · Stakeholders

Stakeholders

Power against interest; click a person to see their role.

Power

Keep satisfied0

Manage closely5

Monitor0

Keep informed0

Eng. Wassim Al-AzmManage closelySalma Al-ZaimManage closelyJwan OthmanManage closelyEng. Maher Al-HamawiManage closelyRasha Al-MudarresManage closely

Interest

Programme decisions

What the committees decided on the programme’s projects, and what the programme raised to them.

Committees

National Projects Steering Committee

Monthly · Quorum ⁦5⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital Transformation
Chair: Dr. Samer Al-DaqqarNext meeting 2026-11-03
Authority Executive Council

Weekly · Quorum ⁦4⁩

Dr. Ziad Al-Atassi · Deputy President, Strategy & PerformanceEng. Abdulrahman Al-Kilani · Deputy President, Development Projects Follow-upEng. Khaled Al-Kayyali · Deputy President, Digital TransformationSalma Al-Zaim · Deputy President, Finance, Administration & the Investment Plan
Chair: Dr. Samer Al-DaqqarNext meeting 2026-10-28
Bid Opening & Award Committee

As needed · Quorum ⁦3⁩

Omar Al-Nahhas · Senior Finance & Contracts SpecialistAbdullah Al-Ujaili · Contracts & Tendering SpecialistEng. Wael Al-Khawlani · Director, Engineering Supervision of Construction ProjectsEng. Rita Ghanem · Enterprise Architect
Chair: Rasha Al-MudarresNo meeting scheduled

Programme projects

The programme’s performance is computed from these projects.

⁦4⁩ results
Export CSV
Manager
Darayya Replacement HousingPRJ-2026-002Eng. Qasem Al-Hariri4ExecutionOff track⁦42%⁩SYP29.5BSYP31.7B⁦+7.5%⁩0.82Schedule performance index · 0.820.93Cost performance index · 0.93
Douma Wastewater Treatment PlantPRJ-2026-020Eng. Qasem Al-Hariri4ExecutionOff track⁦44%⁩SYP8.6BSYP9.1B⁦+5.3%⁩0.80Schedule performance index · 0.800.95Cost performance index · 0.95
Deir ez-Zor Suspension Bridge ReconstructionPRJ-2026-021Eng. Wael Al-Khawlani3PlanningOn track⁦2%⁩SYP13BSYP13B⁦0.0%⁩1.00Schedule performance index · 1.001.00Cost performance index · 1.00
Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernoratePRJ-2026-034Eng. Wael Al-Khawlani4ExecutionAt risk⁦33%⁩SYP6BSYP6.2B⁦+4.2%⁩0.89Schedule performance index · 0.890.96Cost performance index · 0.96
Total · 4SYP57.1BSYP60B
⁦1⁩–⁦4⁩ of ⁦4⁩

Budget shares

Budget shares

SYP 57.1B

Budget

  • Darayya Replacement HousingSYP 29.5B⁦52%⁩
  • Douma Wastewater Treatment PlantSYP 8.6B⁦15%⁩
  • Deir ez-Zor Suspension Bridge ReconstructionSYP 13B⁦23%⁩
  • Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernorateSYP 6B⁦10%⁩
Budget shares
CategoryValueShare
Darayya Replacement HousingSYP 29.5B⁦52%⁩
Douma Wastewater Treatment PlantSYP 8.6B⁦15%⁩
Deir ez-Zor Suspension Bridge ReconstructionSYP 13B⁦23%⁩
Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernorateSYP 6B⁦10%⁩
TotalSYP 57.1B⁦100%⁩