Development Strategic Framework 2026–2030 and the 2026–2028 Medium-Term Plan

Infrastructure projects delivered to plan

Off trackApproved

Rehabilitate core energy, water and transport infrastructure·Reconstruction & Infrastructure

Actual · October

73%

2026 target

⁦85%⁩

Attainment

⁦86%⁩

Year-end forecast

⁦75%⁩

Forecast gap to target

⁦10%⁩

The path from baseline to 2030

Where the KPI stands today between its baseline, this year’s target and the 2030 target.

Baseline

⁦62%⁩

Today

⁦73%⁩

2026 target

⁦85%⁩

2030 target

⁦95%⁩

Left to the 2026 target
⁦12%⁩⁦48%⁩ of the way covered
Left to the 2030 target
⁦22%⁩⁦33%⁩ of the way covered

Monthly series and forecast

January – October measured, November and December forecast with a confidence band; the gold line is the 2026 target.

Monthly series and forecast
  • Actual
  • Baseline
  • Forecast
  • Forecast range
Monthly series and forecast
PeriodActualBaseline
Jan66 %62 %
Feb67 %62 %
Mar68 %62 %
Apr68 %62 %
May69 %62 %
Jun70 %62 %
Jul70 %62 %
Aug71 %62 %
Sep72 %62 %
Oct73 %62 %
Nov (Forecast)74 %62 %
Dec (Forecast)75 %62 %

Period comparison

Quarter by quarter in 2026, the same month last year, and the years since 2024 with the 2026 year-end forecast.

Quarter by quarter — 2026

  1. Q1

    68

  2. Q2

    70

    +2Better

  3. Q3

    72

    +2Better

  4. October

    73

    +1Better

October 2025 vs October 2026

October 2025

60

October 2026

73

+13Better

Years

  • Value
  • 2026 target

Measurement history

Every reading with who entered it, its evidence and its approval. Formal measurement points are marked.

PeriodValueOf targetKindStateEntered byEvidence
October 202673⁦86%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-10-27K-2.1.1_2026-10.pdf
September 202672⁦85%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-10-05K-2.1.1_2026-09.pdf
August 202671⁦84%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-09-04K-2.1.1_2026-08.pdf
July 202670⁦82%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-08-07K-2.1.1_2026-07.pdf
June 202670⁦82%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-07-06K-2.1.1_2026-06.pdf
May 202669⁦81%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-06-05K-2.1.1_2026-05.pdf
April 202668⁦80%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-05-04K-2.1.1_2026-04.pdf
March 202668⁦80%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-04-07K-2.1.1_2026-03.pdf
February 202667⁦79%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-03-06K-2.1.1_2026-02.pdf
January 202666⁦78%⁩Formal measurementApprovedEng. Wassim Al-Azm2026-02-05K-2.1.1_2026-01.pdf

Contributing projects

The projects that move this KPI, and each one’s share of the effect by budget size.

AI insight

Closing the gap runs through one project

The project with the most weight on this KPI is “Deir ez-Zor Suspension Bridge Reconstruction”, with ⁦28%⁩ of the linked budget, and it is On track. Speeding it up is the fastest way to close the gap before December.

Confidence⁦78%⁩

Approval & change log

This item’s definition as approved in the plan version in force, and every change request on it with the old and proposed values and the decision.

Approved in plan version ⁦1.1⁩Higher Council resolution HCED-2026-032026-03-25

No change requests on this item since the plan was approved.

Corrective actions

What we are doing to bring the KPI back on track, who owns it, and by when.

  • Speed up the allocation of the Darayya site’s northern plot with Rif Dimashq Governorate and the electricity transmission & distribution establishment

    Eng. Wassim Al-AzmEng. Wassim Al-AzmDirector General, Infrastructure & Reconstruction ProjectsP-013wassim.alazm@psa.gov.syDue ⁦2026-10-20⁩8 days overdue2026-10-20Darayya Replacement Housing
    Overdue
  • Take the utility networks of the Darayya replacement housing out of the buildings contract and tender them separately

    Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.syDue ⁦2026-11-30⁩In 33 days2026-11-30Darayya Replacement Housing
    In progress

Comments

The owner, the Performance Measurement Office and leadership discussing the readings.

No comments yet. Start the discussion on this KPI.