PRJ-2026-018At risk4ExecutionConstructionIn progressDelivered by:Ministry of Communications and Information Technology

Government Fibre Backbone — Damascus–Homs Segment

Add to watchlist

Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.3B

Actual cost

SYP 1.9B

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 3.4B

+SYP 102.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦52%⁩ chance of a further slip within ⁦45⁩ days

From the SPI trend (⁦0.87⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is behind plan: ⁦55% done against 63% planned⁩.

⁦SPI 0⁩.⁦87⁩, ⁦CPI 0⁩.⁦97⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Governance & Digital TransformationSO-5.2Sound governance and effective follow-up of projects and data

Main initiative

SI-2.1.1National connectivity & support services

Contribution to the initiative⁦36%⁩

The project’s share of the initiative’s project budget (4 projects)

Secondary links

Annual work-plan line
WP-2025-018
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦55%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦35%⁩

6 deliverables accepted

  • Site works & excavation⁦16%⁩
  • Structure⁦16%⁩
  • Detailed design⁦8%⁩
  • Permits & approvals⁦7%⁩
  • Project plan & baseline⁦4%⁩
  • Monitoring & reporting⁦4%⁩

1 deliverable under inspection or acceptance

  • Finishes⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦89%⁩ of budget

SYP1.9B/ SYP3.3BSYP102.1Mprojected overrun(⁦3.1%⁩)
Actual spend
SYP1.9B
Committed
SYP3B
Approved budget
SYP3.3B
Estimate at completion
SYP3.4B

Next milestones

  • Provisional acceptance⁦2027-01-06⁩was ⁦2026-12-12⁩Late
  • Closure⁦2027-03-05⁩was ⁦2027-01-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Risks & impediments

2 open risks, exposure SYP 152.5M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩1Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩RSK-0033City councils objecting to digging in built-up neighbourhoodsProbability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0032Higher reinstatement costs after network trenchingProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium2
  • Low0

Deliverables

⁦6⁩ of ⁦12⁩ approved

  • Project plan & baseline018-D1 · V1 · CRT-018-01⁦4%⁩Eng. George Haddad2025-07-302025-07-30Approved
  • Monitoring & reporting018-D2 · V1 · CRT-018-02⁦4%⁩Eng. Mazen Kassab2025-09-182025-09-18Approved
  • Detailed design018-D3 · V1 · CRT-018-03⁦8%⁩Eng. Mazen Kassab2025-11-072025-11-07Approved
  • Permits & approvals018-D4 · V1 · CRT-018-04⁦7%⁩Eng. Khaled Al-Kayyali2025-12-272025-12-27Approved
  • Site works & excavation018-D5 · V1 · CRT-018-05⁦16%⁩Eng. Khaled Al-Kayyali2026-02-152026-02-15Approved
  • Structure018-D6 · V1 · CRT-018-06⁦16%⁩Eng. George Haddad2026-04-062026-04-06Approved
  • Finishes018-D7 · V1⁦10%⁩Eng. Mazen Kassab155 days overdue2026-05-26In review
  • Supply018-D8 · V0⁦8%⁩Eng. George Haddad105 days overdue2026-07-15Draft
  • Installation018-D9 · V0⁦8%⁩Eng. Mazen Kassab55 days overdue2026-09-03Draft
  • Testing & commissioning018-D10 · V0⁦8%⁩Eng. Khaled Al-Kayyali5 days overdue2026-10-23Draft
  • Provisional acceptance018-D11 · V0⁦6%⁩Eng. Mazen KassabIn 45 days2026-12-12Draft
  • Final acceptance018-D12 · V0⁦5%⁩Eng. Khaled Al-KayyaliIn 95 days2027-01-31Draft

Team, contracts & documents

Team

1 member

Eng. George Haddad · Director, Data Centres & Government Network
  • Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkProject managerP-024george.haddad@psa.gov.sy⁦35%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled