PRJ-2026-018At risk4ExecutionConstructionIn progressDelivered by:Ministry of Communications and Information Technology

Government Fibre Backbone — Damascus–Homs Segment

Add to watchlist

Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.3B

Actual cost

SYP 1.9B

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 3.4B

+SYP 102.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to workSYP3.2B⁦17⁩ elements
Unallocated contingencySYP99MSYP 165M
Budget at completionSYP3.3BPRJ-2026-018
Weighted progress⁦55%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSYP MActualSYP MLinksDeliverables
Project659⁦2025-05-11⁩⁦2027-03-01⁩⁦55%⁩3,201.001,871.13—
1
Phase211⁦2025-05-11⁩⁦2025-12-08⁩⁦100%⁩192.06204.17—
1.1
WBS element130⁦2025-05-11⁩⁦2025-09-18⁩⁦100%⁩96.03102.090 / 1
1.2
WBS element130⁦2025-07-31⁩⁦2025-12-08⁩⁦100%⁩96.03102.091 / 2
2
Phase211⁦2025-10-20⁩⁦2026-05-19⁩⁦100%⁩384.12408.35—
2.1
WBS element130⁦2025-10-20⁩⁦2026-02-27⁩⁦100%⁩192.06204.171 / 1
2.2
WBS element130⁦2026-01-09⁩⁦2026-05-19⁩⁦100%⁩192.06204.171 / 2
3
Phase249⁦2026-03-07⁩⁦2026-11-11⁩⁦97%⁩1,216.381,258.61—
3.1
WBS element130⁦2026-03-31⁩⁦2026-08-08⁩⁦100%⁩405.46431.031 / 1
3.2
WBS element128⁦2026-06-20⁩⁦2026-10-26⁩⁦100%⁩405.46431.031 / 1
3.3
WBS element249⁦2026-03-07⁩⁦2026-11-11⁩⁦92%⁩405.46396.551 / 2
4
Phase80⁦2026-10-28⁩⁦2027-01-16⁩⁦0%⁩960.30——
4.1
WBS element36⁦2026-10-28⁩⁦2026-12-03⁩⁦0%⁩320.10—1 / 1
4.2
WBS element36⁦2026-11-19⁩⁦2026-12-25⁩⁦0%⁩320.10—1 / 1
4.3
WBS element36⁦2026-12-11⁩⁦2027-01-16⁩⁦0%⁩320.10—1 / 2
5
Phase58⁦2027-01-02⁩⁦2027-03-01⁩⁦0%⁩448.14——
5.1
WBS element36⁦2027-01-02⁩⁦2027-02-07⁩⁦0%⁩224.07—1 / 1
5.2
WBS element36⁦2027-01-24⁩⁦2027-03-01⁩⁦0%⁩224.07—1 / 1
Total⁦55%⁩3,201.001,871.13