Original
Original baseline
- Finish
- 2027-01-31
- Budget
- SYP 3.3B
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-05-11 · by Eng. Khaled Al-Kayyali
Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
+SYP 102.1M
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure12 December 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-05-11 · by Eng. Khaled Al-Kayyali
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. George Haddad
What changed from version A to version B
Finish
2027-01-312027-03-01
+29 days
Budget
SYP 3.3BSYP 3.3B
+30.00 SYP M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SYP millions from A to B
Every saved version with its reason and reference