PRJ-2026-018At risk4ExecutionConstructionIn progressDelivered by:Ministry of Communications and Information Technology

Government Fibre Backbone — Damascus–Homs Segment

Add to watchlist

Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.3B

Actual cost

SYP 1.9B

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 3.4B

+SYP 102.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 3.3B split into spent, committed and left, with the estimate at completion

Forecast overrun SYP 102.1M
EAC SYP 3.4B
Revised request SYP 3.3B
  • Actual spendSYP 1.9B
  • Committed, not spentSYP 1.1B
  • Allotted, uncommittedSYP 251M
  • Contingency availableSYP 99M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 2.9B
Original budgetwhen the first baseline was approved
SYP 3.3B
Approved budgetafter approved change requests
SYP 3.3B
Current budgetavailable to spend now
SYP 3.3B
Revised budgetif the pending changes are approved
SYP 3.3B

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 3B
Contracts1 active contract
SYP 2.7B
Purchase orders⁦3⁩ orders
SYP 250M
Remaining budgetapproved less actual
SYP 1.4B

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 1.9B
Accrualswork done, not yet invoiced
SYP 74.8M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 3.4B
ContingencySYP 66M drawn of SYP 165M
SYP 99M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 2.9B
ApprovedSYP 3.3B
Estimate at completionSYP 3.4B
Approved is SYP 362.5M (⁦12.3%⁩) above the estimate
The estimate at completion is SYP 464.6M (⁦15.8%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-02-25⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-61018
  • WBS elements⁦5⁩ elements · P-2026-018.01 …
  • Purchase orders⁦3⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦9⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 66M drawn of SYP 165M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 66M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance192.06204.17204.17204.17⁦−12.11⁩
2Design & permits384.12408.35408.35408.35⁦−24.23⁩
3Civil works1,216.381,258.611,258.611,258.61⁦−42.23⁩
4MEP works960.30735.590.001,010.07⁦−49.77⁩
5Handover448.14343.280.00471.36⁦−23.22⁩
Unallocated contingency99.000.000.0049.50⁦+49.50⁩
Total3,300.002,950.001,871.133,402.06⁦−102.06⁩

Budget split

WBS

SYP 3.3B

Budget

  • Management & governanceSYP 192.1M⁦6%⁩
  • Design & permitsSYP 384.1M⁦12%⁩
  • Civil worksSYP 1.2B⁦37%⁩
  • MEP worksSYP 960.3M⁦29%⁩
  • HandoverSYP 448.1M⁦14%⁩
  • Unallocated contingencySYP 99M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-02-17⁩+382

SPI(t) ⁦0.62⁩ against the approved finish ⁦2027-01-31⁩

Planned valuePV
SYP 3.1B
The value of the work that should be done by today.
PV
Earned valueEV
SYP 1.8B
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 1.9B
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 3.3B
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−56.13⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1,302.20⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.97
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.58
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 3.4B
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 1.5B
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−102.06⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.04
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 3.4B
  • If the rest goes to planSYP 3.4B
  • At cost and schedule performanceSYP 4.5B
  • The PM’s bottom-up estimateSYP 3.4B
  • To stay within SYP 3.3B, cost performance on the rest must rise to ⁦1.04⁩ — above what has been achieved.

Estimate at completion at that performance

SYP 3.4B

Variance at completion: ⁦−102.06⁩ SYP M