PRJ-2026-018At risk4ExecutionConstructionIn progressDelivered by:Ministry of Communications and Information Technology

Government Fibre Backbone — Damascus–Homs Segment

Add to watchlist

Laying a government fibre backbone between Damascus and Homs that links the ministries’ directorates and the main and backup data centres — the first segment of the network that will reach every governorate.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SYP 3.3B

Actual cost

SYP 1.9B

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 3.4B

+SYP 102.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Closure readiness

Closure planned after the forecast finish on ⁦2027-03-05⁩

A preview of what closure will need, with the planned dates, and the lessons captured so far.

0/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedNot started

    Final acceptance of every deliverable

    Eng. Mazen KassabPlanned ⁦2027-02-23⁩

  2. 2

    Financial closureNot started

    Spend reconciled, commitments closed

    Omar Al-NahhasPlanned ⁦2027-03-25⁩

  3. 3

    Contract closureNot started

    Contracts closed, bonds released

    Omar Al-NahhasPlanned ⁦2027-04-04⁩

  4. 4

    Documents archivedNot started

    Documents archived with classification

    Eng. George HaddadPlanned ⁦2027-03-30⁩

  5. 5

    Lessons learnedNot started

    Lessons-learned session

    Eng. George HaddadPlanned ⁦2027-03-20⁩

  6. 6

    Benefits owner assignedNot started

    Benefits handed to their owner with a measurement plan

    Eng. Mazen KassabPlanned ⁦2027-03-15⁩

  7. 7

    Final report approvedNot started

    Final report and its approval

    Eng. George HaddadPlanned ⁦2027-04-09⁩

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

The review comes after closure

About three months after the forecast finish (⁦2027-03-05⁩), with the sponsor and the benefits owner.

Lessons learned

0 lessons — offered automatically to similar projects when they are created.

Knowledge base

No lessons captured yet

Capture what the team learned during delivery; closure needs at least one.

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.

No benefits recorded for this project.