PRJ-2026-030On track5ClosureWaterfallIn progressDelivered by:Planning and Statistics Authority

National Project Risk & Continuity Framework

Add to watchlist

One policy and set of registers for national project risk and business continuity, adopted by the ministries, with training for risk coordinators.

Project managerNizar Abu FakhrProject sponsorDr. Ziad Al-Atassi

Budget (BAC)

SYP 90M

Actual cost

SYP 86.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 86.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Closing

⁦4⁩ of ⁦7⁩ closure items done

Finish the open items and hand the benefits to their owner, then close the project. No project closes without lessons learned.

4/7

Closure checklist

Seven mandatory items before any project closes.

  1. 1

    Deliverables acceptedDone

    Framework, policies and risk appetite approved by the national steering committee

    Dr. Mais Al-SibaiDone ⁦2026-08-31⁩

  2. 2

    Financial closureIn progress

    ⁦Reconciling SYP 86⁩.⁦5M spend⁩; closing the last SYP ⁦1M of commitments⁩

    Huda Al-DandalPlanned ⁦2026-11-05⁩

  3. 3

    Contract closureDone

    No external contracts — delivered in-house

    Nizar Abu FakhrDone ⁦2026-09-10⁩

  4. 4

    Documents archivedIn progress

    ⁦31 of 38 documents archived⁩

    Nizar Abu FakhrPlanned ⁦2026-11-02⁩Evidence

  5. 5

    Lessons learnedDone

    One lesson published on ministry risk coordinators

    Nizar Abu FakhrDone ⁦2026-10-14⁩Evidence

  6. 6

    Benefits owner assignedNot started

    Hand the response-plan benefit from the PM to the Director General, Strategy & National Projects

    Dr. Mais Al-SibaiPlanned ⁦2026-10-31⁩

    Hand over benefits ↓
  7. 7

    Final report approvedDone

    ⁦Closure report V1 approved⁩

    Nizar Abu FakhrDone ⁦2026-10-14⁩Evidence

Post-implementation review

Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?

· Facilitated by Dr. Reem Al-Qabbani

Did it reach its goal?

Yes

100%

Every deliverable done; the national steering committee approved the risk appetite.

Did it stay on budget?

Yes

−3.9%

⁦SYP 86⁩.⁦5M against⁩ ⁦90M⁩, on time.

Were the benefits realised?

Partly

78%

⁦78% of risks have a response plan vs 90% targeted at 12 months⁩.

What did we learn?

Yes

1

One lesson published; a second proposed on linking the register to Munjaz.

What should improve?

Partly

—

To complete in the post-closure review session.

Lessons learned

1 lesson — offered automatically to similar projects when they are created.

Knowledge base
LL-035Stakeholderscited ⁦2⁩ times

Name a project champion in every sector from day one

Context
A national project risk framework needs every delivering ministry involved.
What happened
Two sectors lagged until a named coordinator was set for each.
Impact
⁦Risks with a response plan rose from 35% to 78%⁩.
Recommendation
Add a “sector champion” role to the communication-plan template.
Nizar Abu Fakhr · ⁦2026-09-28⁩

Benefits handover

Each benefit moves from the project manager to an owner who measures it after closure.