PRJ-2026-030On track5ClosureWaterfallIn progressDelivered by:Planning and Statistics Authority

National Project Risk & Continuity Framework

Add to watchlist

One policy and set of registers for national project risk and business continuity, adopted by the ministries, with training for risk coordinators.

Project managerNizar Abu FakhrProject sponsorDr. Ziad Al-Atassi

Budget (BAC)

SYP 90M

Actual cost

SYP 86.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 86.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦100% done against 100% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦04⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Governance & Digital TransformationSO-5.2Sound governance and effective follow-up of projects and data

Main initiative

SI-5.2.2Performance measurement, monitoring & evaluation

Contribution to the initiative⁦22%⁩

The project’s share of the initiative’s project budget (3 projects)

Secondary links

No secondary links

Annual work-plan line
Added outside the annual work plan
Classification
Operational

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦100%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦0%⁩

10 deliverables accepted

  • Target model⁦15%⁩
  • Roadmap⁦15%⁩
  • Wave 1⁦15%⁩
  • Wave 2⁦15%⁩
  • Current-state assessment⁦10%⁩
  • Benchmarking⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦5⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦97%⁩ of budget

    SYP86.5M/ SYP90MSYP3.5Mprojected saving(⁦3.8%⁩)
    Actual spend
    SYP86.5M
    Committed
    SYP87.5M
    Approved budget
    SYP90M
    Estimate at completion
    SYP86.5M

    Next milestones

    • Every milestone is complete

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • Record lessons learned from the national risk frameworkNizar Abu Fakhr2026-10-202026-10-20Low

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SYP 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦10⁩ of ⁦10⁩ approved

    • Project plan & baseline030-D1 · V1 · CRT-030-01⁦5%⁩Nizar Abu Fakhr2025-05-302025-05-30Approved
    • Monitoring & reporting030-D2 · V1 · CRT-030-02⁦5%⁩Dr. Mais Al-Sibai2025-07-192025-07-19Approved
    • Current-state assessment030-D3 · V1 · CRT-030-03⁦10%⁩Dr. Mais Al-Sibai2025-09-082025-09-08Approved
    • Benchmarking030-D4 · V1 · CRT-030-04⁦10%⁩Dr. Ziad Al-Atassi2025-10-292025-10-29Approved
    • Target model030-D5 · V1 · CRT-030-05⁦15%⁩Dr. Ziad Al-Atassi2025-12-192025-12-19Approved
    • Roadmap030-D6 · V1 · CRT-030-06⁦15%⁩Nizar Abu Fakhr2026-02-082026-02-08Approved
    • Wave 1030-D7 · V1 · CRT-030-07⁦15%⁩Nizar Abu Fakhr2026-03-312026-03-31Approved
    • Wave 2030-D8 · V1 · CRT-030-08⁦15%⁩Dr. Mais Al-Sibai2026-05-212026-05-21Approved
    • Knowledge transfer030-D9 · V1 · CRT-030-09⁦5%⁩Dr. Mais Al-Sibai2026-07-112026-07-11Approved
    • Final report030-D10 · V1 · CRT-030-10⁦5%⁩Dr. Ziad Al-Atassi2026-08-312026-08-31Approved

    Team, contracts & documents

    Team

    2 members

    Nizar Abu Fakhr · Head, Monitoring, Evaluation & PerformanceDr. Reem Al-Qabbani · Director, National Project Management Office
    • Nizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceProject manager (closure)P-040nizar.abufakhr@psa.gov.sy⁦20%⁩
    • Dr. Reem Al-QabbaniDr. Reem Al-QabbaniDirector, National Project Management OfficeClosure assurance & lessons learnedP-002reem.alqabbani@psa.gov.sy⁦15%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house