PRJ-2026-030On track5ClosureWaterfallIn progressDelivered by:Planning and Statistics Authority

National Project Risk & Continuity Framework

Add to watchlist

One policy and set of registers for national project risk and business continuity, adopted by the ministries, with training for risk coordinators.

Project managerNizar Abu FakhrProject sponsorDr. Ziad Al-Atassi

Budget (BAC)

SYP 90M

Actual cost

SYP 86.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 86.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

5Achieved
0On track
0At risk
0Late
Average delay36 days
Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-02-08⁩Forecast / actual: ⁦2026-03-16⁩Delay: 36 daysG3 +36
Executive
Project plan approvedPlanned: ⁦2025-07-19⁩Forecast / actual: ⁦2025-08-03⁩Delay: 15 daysG1 +15
Payment
Final handoverPlanned: ⁦2026-08-31⁩Forecast / actual: ⁦2026-10-26⁩Delay: 56 daysG5 +56
Regulatory
Testing & acceptance completePlanned: ⁦2026-05-21⁩Forecast / actual: ⁦2026-07-07⁩Delay: 47 daysG4 +47
Project
Designs approvedPlanned: ⁦2025-10-29⁩Forecast / actual: ⁦2025-11-24⁩Delay: 26 daysG2 +26

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-07-19⁩⁦2025-08-03⁩⁦+15⁩ daysNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syAchieved1Approved
Designs approvedMS-G2Project⁦2025-10-29⁩⁦2025-11-24⁩⁦+26⁩ daysNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syAchieved1Approved
Build completeMS-G3Contractual⁦2026-02-08⁩⁦2026-03-16⁩⁦+36⁩ daysNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-05-21⁩⁦2026-07-07⁩⁦+47⁩ daysNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syAchieved1Approved
Final handoverMS-G5Payment⁦2026-08-31⁩⁦2026-10-26⁩⁦+56⁩ daysNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syAchieved1Approved
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦100%⁩

Awaiting acceptance

⁦0%⁩

Not handed in

⁦0%⁩

Deliverable flow

Pick a stage to filter the register
⁦10⁩ results
Export CSV
Project plan & baseline030-D1⁦5%⁩CRT-030-01ApprovedNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syDr. Mais Al-Sibai⁦2025-05-30⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting030-D2⁦5%⁩CRT-030-02ApprovedDr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.syDr. Mais Al-Sibai⁦2025-07-19⁩V1⁦3⁩ of ⁦3⁩
Current-state assessment030-D3⁦10%⁩CRT-030-03ApprovedDr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.syDr. Mais Al-Sibai⁦2025-09-08⁩V1⁦3⁩ of ⁦3⁩
Benchmarking030-D4⁦10%⁩CRT-030-04ApprovedDr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syDr. Mais Al-Sibai⁦2025-10-29⁩V1⁦3⁩ of ⁦3⁩
Target model030-D5⁦15%⁩CRT-030-05ApprovedDr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syDr. Mais Al-Sibai⁦2025-12-19⁩V1⁦3⁩ of ⁦3⁩
Roadmap030-D6⁦15%⁩CRT-030-06ApprovedNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syDr. Mais Al-Sibai⁦2026-02-08⁩V1⁦3⁩ of ⁦3⁩
Wave 1030-D7⁦15%⁩CRT-030-07ApprovedNizar Abu FakhrNizar Abu FakhrHead, Monitoring, Evaluation & PerformanceP-040nizar.abufakhr@psa.gov.syDr. Mais Al-Sibai⁦2026-03-31⁩V1⁦3⁩ of ⁦3⁩
Wave 2030-D8⁦15%⁩CRT-030-08ApprovedDr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.syDr. Mais Al-Sibai⁦2026-05-21⁩V1⁦3⁩ of ⁦3⁩
Knowledge transfer030-D9⁦5%⁩CRT-030-09ApprovedDr. Mais Al-SibaiDr. Mais Al-SibaiDirector General, Strategy & National ProjectsP-015mais.alsibai@psa.gov.syDr. Mais Al-Sibai⁦2026-07-11⁩V1⁦3⁩ of ⁦3⁩
Final report030-D10⁦5%⁩CRT-030-10ApprovedDr. Ziad Al-AtassiDr. Ziad Al-AtassiDeputy President, Strategy & PerformanceP-009ziad.alatassi@psa.gov.syDr. Mais Al-Sibai⁦2026-08-31⁩V1⁦3⁩ of ⁦3⁩
Total · 10⁦100%⁩
⁦1⁩–⁦10⁩ of ⁦10⁩