PRJ-2026-030On track5ClosureWaterfallIn progressDelivered by:Planning and Statistics Authority

National Project Risk & Continuity Framework

Add to watchlist

One policy and set of registers for national project risk and business continuity, adopted by the ministries, with training for risk coordinators.

Project managerNizar Abu FakhrProject sponsorDr. Ziad Al-Atassi

Budget (BAC)

SYP 90M

Actual cost

SYP 86.5M

⁦96%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 86.5M

SPI · CPI

1.00Schedule performance index · 1.001.04Cost performance index · 1.04

Forecast finish

⁦2026-08-31⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
PSA-PMO-F12
Template edition
2.0
Version
V1
Form date
⁦2026-10-12⁩
In approvalPRJ-2026-030National Project Risk & Continuity Framework

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-030
Project
National Project Risk & Continuity Framework
Portfolio
Planning, Statistics & Capability Portfolio
Sector
Strategy & National PMO Sector
Sponsor
Dr. Ziad Al-Atassi
Project manager
Nizar Abu Fakhr

1PerformanceAuto-filled

Approved budget

SYP 90M

Actual cost

SYP 86.5M

Cost variance

+SYP 3.5M

Schedule variance

0 days

Post-implementation questionVerdictAnswer
Did the project meet its goal?YesEvery deliverable done; the national steering committee approved the risk appetite.
Was it delivered within budget?YesSYP 86.5M against 90M, on time.
Are the benefits showing?Partly78% of risks have a response plan vs 90% targeted at 12 months.
Were the lessons captured?YesOne lesson published; a second proposed on linking the register to Munjaz.
What to improve next time?PartlyTo complete in the post-closure review session.

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesDoneDr. Mais Al-SibaiFramework, policies and risk appetite approved by the national steering committee
Financial settlementIn progressHuda Al-DandalReconciling SYP 86.5M spend; closing the last SYP 1M of commitments
Contracts closedDoneNizar Abu FakhrNo external contracts — delivered in-house
Documents archivedIn progressNizar Abu Fakhr31 of 38 documents archived
Lessons learnedDoneNizar Abu FakhrOne lesson published on ministry risk coordinators
Benefits handed to their ownerOpenDr. Mais Al-SibaiHand the response-plan benefit from the PM to the Director General, Strategy & National Projects
Final reportDoneNizar Abu FakhrClosure report V1 approved
BenefitNew ownerHandover
National project risks with response & continuity plansDr. Mais Al-SibaiPending

3Open commitments

CommitmentOwnerDue
Financial settlement — Reconciling SYP 86.5M spend; closing the last SYP 1M of commitmentsHuda Al-Dandal⁦2026-11-05⁩
Documents archived — 31 of 38 documents archivedNizar Abu Fakhr⁦2026-11-02⁩
Benefits handed to their owner — Hand the response-plan benefit from the PM to the Director General, Strategy & National ProjectsDr. Mais Al-Sibai⁦2026-10-31⁩

4Lessons learnedAuto-filled

  1. Name a project champion in every sector from day one

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Nizar Abu FakhrHead, Monitoring, Evaluation & PerformanceSubmitted—⁦2026-10-12⁩ 11:56
2Closure file completenessMethodology reviewApproval enginePMO — analystPre-breach alert—⁦2026-10-15⁩ 08:00
3Closure file completenessMethodology reviewApproval engineEscalated automatically to PMO — director (Dr. Reem Al-Qabbani) on ⁦2026-10-19⁩Automatic escalation—⁦2026-10-19⁩ 08:05

Signatures

Closure file completeness

Mariam Al-Zoubi

Awaiting decision

Handover accepted — project owner

Dr. Mais Al-Sibai

Later

Final financial settlement

Rasha Al-Mudarres

Later

Project Approval Committee

Dr. Reem Al-Qabbani

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F12 · version V1

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Submitted by Nizar Abu Fakhr on ⁦2026-10-12⁩

  1. Methodology review

    Closure file completeness

    Mariam Al-Zoubi · PMO — analyst

    Delegated to Dr. Reem Al-Qabbani

    9 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-15⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-10-15⁩

    Escalated automatically to PMO — director (Dr. Reem Al-Qabbani) on ⁦2026-10-19⁩

  2. Technical acceptance

    Handover accepted — project owner

    Dr. Mais Al-Sibai · Project owner

    Limit 3 working days · Expected by ⁦2026-10-20⁩

  3. Financial approval

    Final financial settlement

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

    Limit 3 working days · Expected by ⁦2026-10-25⁩

  4. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Limit 5 working days · Expected by ⁦2026-11-01⁩

Steps that do not apply to this record

  • Contracts closed, guarantees released — the condition «Contract link?» does not hold

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-10-12⁩

    The closure file in preparation

    Nizar Abu Fakhr

Only one version so far.