Portfolio · PF-INF
Reconstruction & Infrastructure Portfolio
Off track
Darayya replacement housing, the Douma treatment plant, the Deir ez-Zor suspension bridge, Maarat al-Numan, the southern M5, the fibre backbone, the census and the government contact centre.
5 projects in this portfolio are pulling its health down
Most of it comes from “Douma Wastewater Treatment Plant” (SPI 0.80) and “Darayya Replacement Housing” (SPI 0.82). Fixing those two lifts the portfolio towards 67 within two quarters.
Portfolio progress = Σ (project relative weight × actual progress). Relative weight = the project’s weight ÷ the weights of the counted projects, so they add up to 100%.
· Proposed and cancelled projects never count.
· Left out of this portfolio now: 1
· For comparison: weighting by budget alone gives 32.8%
8Unified Government Contact Centre & AI AssistantPRJ-2026-024·Priority score 64On track
Portfolio priorities 2026–2027
Clear the groundwater block at the Douma treatment plant on the programme’s critical pathDewatering on axes 12–16 is five months late, and the Darayya replacement housing’s sewer networks wait on the plant.
Hand over 60 rehabilitated public facilities this year48 handed over to October.
Offer the shops in the Darayya replacement housing for investmentMoves attracted investment toward target.