RSK-0036Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

City council late clearing rubble and opening access roads to the work sites

16HighOpenMaterial

A risk's detail, response, contingency and residual risk.

Risk statement

From cause to event to impact — with the preventive controls before the event and the contingency after it

Cause

Price swings and unplanned financial commitments

Preventive controls

  • Monthly EAC monitoring
  • Fix prices in the coming purchase orders

2 / 2

Event

City council late clearing rubble and opening access roads to the work sites

16HighTrigger

EAC above budget by more than 5%

Contingency

Reallocate from the portfolio reserve

Impact

Budget overrun and the need for more funding

SYP 350M

Assessment

The level before and after the response

Inherent

5
4
3
2
1
1
2
3
4
5
16High

Residual

5
4
3
2
1
1
2
3
4
5
6Low

Exposure

SYP 350M

Residual

⁦63⁩% off the score

Score trend

Last six months

  • Score
  • Target residual

Escalation path

Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director

Last reviewed 56 days ago

  1. Project manager

    Eng. Wael Al-Khawlani

    Currently followed up here
  2. Programme manager

    Eng. Qasem Al-Hariri

    Automatically at 15 days unreviewed · threshold passed 41 days ago
  3. PMO director

    Current level

    Dr. Reem Al-Qabbani

    Automatically at 20 days unreviewed · threshold passed 36 days ago
  4. 4

    Executive Council

    Dr. Samer Al-Daqqar

    By the PMO director’s decision

Mitigation plan

Each action with its owner and date — tick it off when complete

⁦0⁩ of ⁦2⁩ done
  • Monthly EAC monitoring

    Dr. Firas Al-ObaidDr. Firas Al-ObaidDeputy President, StatisticsP-016firas.alobaid@psa.gov.sy
    In progressIn 64 days2026-12-31
  • Fix prices in the coming purchase orders

    Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy
    Not startedIn 64 days2026-12-31

Trigger

EAC above budget by more than 5%

Contingency

Reallocate from the portfolio reserve

Esc