PRJ-2026-034At risk4ExecutionConstructionIn progressDelivered by:Ministry of Public Works and Housing

Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate

Add to watchlist

Rehabilitating roads, water and drainage networks and street lighting in Maarat al-Numan with Idlib Governorate, so residents and public services can return.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SYP 6B

Actual cost

SYP 2B

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SYP 6.2B

+SYP 247.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−8

May to October 2026

No material change in the health dimensions over the period.

AI insight

⁦55%⁩ chance of a further slip within ⁦60⁩ days

From the SPI trend (⁦0.89⁩), the task closure rate and the open risks, the early-warning engine expects another slip unless the resource gap is closed.

Confidence⁦82%⁩

Copilot summary

Generated from the live project data

The project is close to plan: ⁦33% done against 37% planned⁩.

⁦SPI 0⁩.⁦89⁩, ⁦CPI 0⁩.⁦96⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: Reconstruction & InfrastructureSO-2.2Rebuild damaged areas and provide replacement housing

Main initiative

SI-6.1.1Service projects in the governorates

Contribution to the initiative⁦100%⁩

The project’s share of the initiative’s project budget (1 project)

Secondary links

Annual work-plan line
WP-2025-034
Classification
External

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦33%⁩

Awaiting acceptance ⁦12%⁩

Not handed in ⁦55%⁩

5 deliverables accepted

  • Site works & excavation⁦14%⁩
  • Detailed design⁦7%⁩
  • Permits & approvals⁦6%⁩
  • Project plan & baseline⁦3%⁩
  • Monitoring & reporting⁦3%⁩

1 deliverable under inspection or acceptance

  • Structure⁦12%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦86%⁩ of budget

SYP2B/ SYP6BSYP247.9Mprojected overrun(⁦4.2%⁩)
Actual spend
SYP2B
Committed
SYP5.1B
Approved budget
SYP6B
Estimate at completion
SYP6.2B

Next milestones

  • Provisional acceptance⁦2027-07-20⁩was ⁦2027-06-29⁩Late
  • Closure⁦2027-09-28⁩was ⁦2027-08-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦1⁩ open action on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦1⁩ open

  • Complete the August and September progress reportsEng. Wael Al-Khawlani13 days overdue2026-10-15Medium

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SYP 350M

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩1Probability: Likely · Impact: MajorHigh · Score ⁦16⁩RSK-0036City council late clearing rubble and opening access roads to the work sitesProbability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High1
  • Medium0
  • Low0

Deliverables

⁦5⁩ of ⁦12⁩ approved

  • Project plan & baseline034-D1 · V1 · CRT-034-01⁦3%⁩Eng. Wael Al-Khawlani2025-10-142025-10-14Approved
  • Monitoring & reporting034-D2 · V1 · CRT-034-02⁦3%⁩Eng. Fadi Al-Droubi2025-12-152025-12-15Approved
  • Detailed design034-D3 · V1 · CRT-034-03⁦7%⁩Eng. Fadi Al-Droubi2026-02-162026-02-16Approved
  • Permits & approvals034-D4 · V1 · CRT-034-04⁦6%⁩Eng. Abdulrahman Al-Kilani2026-04-192026-04-19Approved
  • Site works & excavation034-D5 · V1 · CRT-034-05⁦14%⁩Eng. Abdulrahman Al-Kilani2026-06-202026-06-20Approved
  • Structure034-D6 · V1⁦12%⁩Eng. Wael Al-Khawlani67 days overdue2026-08-22Submitted
  • Finishes034-D7 · V0⁦12%⁩Eng. Fadi Al-Droubi5 days overdue2026-10-23Draft
  • Supply034-D8 · V0⁦10%⁩Eng. Wael Al-KhawlaniIn 57 days2026-12-24Draft
  • Installation034-D9 · V0⁦10%⁩Eng. Fadi Al-DroubiIn 120 days2027-02-25Draft
  • Testing & commissioning034-D10 · V0⁦9%⁩Eng. Abdulrahman Al-KilaniIn 182 days2027-04-28Draft
  • Provisional acceptance034-D11 · V0⁦7%⁩Eng. Fadi Al-DroubiIn 245 days2027-06-30Draft
  • Final acceptance034-D12 · V0⁦7%⁩Eng. Abdulrahman Al-KilaniIn 307 days2027-08-31Draft

Team, contracts & documents

Team

2 members

Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction ProjectsEng. Adnan Al-Mohammad · Senior Site Engineer (Contractor)
  • Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsProject managerP-036wael.alkhawlani@psa.gov.sy⁦70%⁩
  • Eng. Adnan Al-MohammadEng. Adnan Al-MohammadSenior Site Engineer (Contractor)Site engineerP-043adnan.almohammad@psa.gov.sy⁦60%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled